HomeMy WebLinkAboutMINUTES - 10011991 - 1.7 BOARD ORDER FOR PROJECT ADVERTISING
TO: BOARD OF SUPERVISORS, AS THE GOVERNING BODY OF THE CONTRA COSTA
COUNTY SANITATION DISTRICT NO. 15
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: October 1, 1991
SUBJECT: Approving Plans and Specifications and Advertise for bids for the Sunset Lane Sewer
Line Project.
Project No. 7392-6X9E78-90, CP #90-18.
Specific Request(s) or Recommendation(s) & Background & Justification
I. RECOMMENDED ACTION:
APPROVE the Plans and Specifications for the Project and
ADVERTISE for bids to be received on Thursday, October 31, 1991, at 2:00 p.m.
DIRECT the Clerk of the Board to publish the Notice to Contractors in accordance with Section
20783 of the Public Contract Code.
II. FINANCIAL IMPACT:
The estimated contract cost of the project is $8,675.00, funded by Sanitation District No. 15
(100%)
Continued on Attachment: X SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON OCT 1 1991 APPROVED AS RECOMMENDED X OTHER
(f
VOTE OF SUPERVISORS
UNANIMOUS (ABSENT - )
AYES: NOES:
ABSENT: ABSTAIN:
ES:jlg
c\BO:Sunset.tl0
! hereby certify that this Is a true and correct copy of
an action taken and entered on the minutes of the
Orig. Div: Public Works (Design Division) Board of SuperOsQrsthe 099 shown.
cc: County Administrator ATTESTED: O C ! I�
91
Attn: E. Kuevor PHIL BATCHELOR,Clark of the Board
Auditor-Controller of Supervisors and County Administrator
PW Accounting BY rt ,- ,�..,Deputy
Construction
Community Development
y /, ,7
SUBJECT: Approving Plans and Specifications and Advertise for bids for the Sunset Lane Sewer
Line Project.
Project No. 7392-6X9E78-90, CP #90-18.
October 1, 1991
Page Two
III. REASONS FOR RECOMMENDATION/BACKGROUND:
The project is needed to comply with Resolution 89/419, which required houses using septic
tanks to connect to a public sewer and required the Chief Engineer to prepare these Plans and
Specifications. The Chief Engineer has filed with the Board of Supervisors the Plans and
Specifications for the project.
The general prevailing rates of wages, which shall be the minimum rates paid on this project,
have been filed with the Clerk of the Board and copies will be made available to any interested
parry upon request.
The Board reviewed and approved the project on September 11, 1990 and determined the
project to be exempt from the California Environmental Quality Act as a Class 3 Categorical
Exemption. A notice of Exemption was filed with the County Clerk on September 19, 1990.
IV. CONSEQUENCES OF NEGATIVE ACTION:
If the project is not approved for advertising, it will not be constructed and the provisions of
Resolution No. 89/419 will not be met.