HomeMy WebLinkAboutMINUTES - 01221991 - 1.4 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: January 22, 1991
SUBJECT: Approve Addendum No. 2 for Highway 4 Widening-Big Break Road to Empire Avenue
Project No.: 4660-6X4014-89
SPECIFIC REQUEST(S) OR RECOMMENDATIONS) &BACKGROUND AND JUSTIFICATION
I. Recommended Action:
APPROVE prior issuance of Addendum No. 2 to the Notice to Contractors and Proposal for Bids
for Highway 4 Widening, Big Break Road to Empire Avenue, in the Oakley area.
II. Financial Impact:
This addendum does not result in a change to the estimated project cost.
III. Reasons for Recommendations and Background:
On December 11, 1990 the Board of Supervisors approved the plans and specifications for this
project. This addendum reduces the percentage of contract work that the Contractor must
perform with his/her own organization from 50 percent to 30 percent. The reduction is
necessary due to the significant amount of specialty work.
IV. Consequences of Negative Action:
If this addendum is not approved fewer contractors may qualify:"to submit bids for the project
�j
Continued on Attachment:_ SIGNATURE:
_ RECOMMENDATION OF COUNTY ADMINISTRATOR
_ RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON JAIV 2 1991 APPROVED AS RECOMMENDED X_ OTHER
VOTE OF SUPERVISORS
UNANIMOUS (ABSENT )
AYES: NOES:
ABSENT: ABSTAIN: I hereby certify that this Is a true and correct copy of
an action taken and entered on the minutes of the
RH:drg Board of Supervi 22 d�991�
C\BO:22.tl ATTESTED:
PHIL BATCHELOR,Clerk of the Board
Orig. Div: Public Works (Design Division) of Supervisors and County Administrator
cc: County Admin-E. Kuevor
Auditor/Controller
BY �w.__ i.� e.li .Deputy
PW Accounting
Construction