SUBJECT: Martinez Parking and Transit Improvement Project
SPECIFIC REQUEST(S) OR RECOMMENDATION(S) & BACKGROUND AND JUSTIFICATION
RECOMMENDATION:
Adopt the attached resolution supporting an application by the City of
Martinez to the California Transportation Commission, via Caltrans, for
Proposition 116 Rail Bond funds for the Martinez Parking and Transit
Improvement Project, and to direct the County Administrator and the
Director of Community Development to report to the Board on other
opportunities available to the County to support the City' s Parking and
_ .Transit Improvement Project.
FINANCIAL IMPACT
None. There is no financial impact associated with endorsing the
submission of an application of funds, or with identifying
opportunities available to the County to support the project.
REASONS FOR RECOMMENDATIONS/BACKGROUND:
Over the past several years, the County has taken a number of actions
to address the parking needs of jurors, County employees and rail
patrons. The results of the Joint Parking Study in 1987 undertaken in
cooperation with the. City of Martinez and the Contra Costa Community
College District clearly indicate that additional parking is needed to
address the short and long term needs of the downtown area.
In addition, the ACR 132 , Intercity Rail Corridor Upgrade Study
recommends the development of a project "which would be available to
intercity rail passengers as well as employees and customers in the
greater downtown area. " (ACR 132 Report, page B-11) Supervisor
Schroder represented the County on the study' s Policy Steering
Committee. On March 20, 1990, the Board adopted resolution 90/167
supporting action by the Policy Steering Committee to increase rail
service at the Martinez AMTRAK station.
The Transportation Committee reviewed a report from the City of
Martinez on the Parking and Transit Improvement Project (see Exhibit
A) . Based on this information and past Board action, the Committee
prepared the attached resolution supporting the city's project (see
Exhibit B) and recommends its adoption by the Board.
Orig.Dept: CDD-TP
CONTINUED ON ATTACHMENT: YES SIGNATURE:
XX
RECOMMENDATION OF COU Y TRATOR RECOMMENDATION OF BOARD COMMITTEE
APPROVE
`ao" ",,,,.A //�/y�
�
SIGNATURE(S): Sc der Tom Torlakson
ACTION OF BOARD ON
SUR Imi APPROVED AS RECOMMENDED X OTHER
VOTE OF SUPERVISORS
+� 1 HEREBY CERTIFY THAT THIS IS A TRUE
UNANIMOUS (ABSENT Ir .. ) AND CORRECT COPY OF AN ACTION TAKEN
AYES: NOES: AND ENTERED ON THE MINUTES OF THE BOARD
ABSENT: ABSTAIN: - OF SUPERVISORS ONTHE
(�DATE SHOWN.
I
CC' City of Martinez ATTESTED, FEB 26 1991
Community Development PHIL BATCHELOR. CLERK OF THE BOARD OF
SUPERVISORS AND COUNTY ADMINISTRATOR
M382/7-83 BY K' a1L1aL ��• DEPUTY
E X H I B I T A
PARKING AND TRANSIT IMPROVEMENT PROJECT
BACKGROUND INFORMATION
Downtown Martinez is home to a number of significant public use facilities.
It is the seat of Contra Costa County including Superior Courts, the adminis-
trative center of the Contra Costa Community College District, and the
Martinez Train Station served by Amtrak interstate and San Joaquin trains as
well as"Fun Trains" and Transciso Tour .trains to Reno and Truckee.
One result of the location of these major activities in the downtown Martinez
area are significant parking and transportation access problems. The increase
in train service to Martinez as well as the anticipated level of court and
other governmental uses has precipitated the City' s request to work with
affected local and State entities to address these problems
The ACR 132 Study indicates that there is a short term parking need at the
train station of 125-175 spaces. For this analysis, short term is defined as
the beginning of 12 train service in FY 1993/94. However, parking shortfalls
could be experienced as soon as additional train service is introduced within
_ the year. Long term needs for the station, keyed to year 2010 patronage
estimates, include 300-425 additional spaces for a station parking deficiency
of 425 to 600 spaces.
In addition, parking needs for the downtown area, based on the parking study
jointly undertaken by the City of Martinez, Contra Costa County and the Contra
Costa Community College District in 1987, indicate the current parking need at
160 spaces and the long term need (year 1995) at 460 spaces, exclusive of any
spaces for the station.
As a result, the total short term parking need in the vicinity of the station
ranges from 285 to 335 spaces. Long term needs range from 760 to 885 addit-
ional spaces or a an unmet parking need of 1045 to 1220 spaces.
The ACR 132 Study indicates that the "implementation of the intercity rail
service should be coordinated with existing planning efforts being made by the
City and County." (ACR 132, p.B-11) The report further recommends exploration
of two alternatives to meet the parking demand. First, the development of
additional parking facilities dedicated to rail passengers which would place
the burden of additional parking on other than local entities. The second
alternative is "participation in financing of other public facilities which
would be available to intercity rail -passengers as well as employees and
customers in the greater downtown area." It is anticipated that jurors are
included in the definition of customers using the downtown and civic use area.
The Parking and Transit Improvement Project is intended to the address parking
and transportation access issues in the greater downtown area. In addition to
additional parking, project alternatives will include improvements to the bus
loading zone at the station. The current bus loading area is no longer
sufficient to serve the increased_ number of busses accessing the station.
Further, bus access and egress on local streets should be improved to elimi-
nate current operational difficulties and to allow for a higher level of
service in the future. Project alternatives may need to allow for the
aggregation of existing parking facilities in order to accommodate an improved
bus loading area , better pedestrian access and external passenger waiting
areas as well as the installation of bicycle storage facilities and improved
accessibility -features.
Project Alternatives
A number of project alternatives have been defined to begin the public
participation discussion on alternatives to be analyzed in an environmental
assessment. Alternatives currently include:
1) No project
2) TSM improvements
3) Structure parking options using publicly owned land on the south side
of the Station
4) Surface parking on the north side of the Station.
All but the "no project" alternative will include improvements to the bus
access and loading areas, improved external passenger waiting areas, installa-
tion of bicycle storage facilities, reallocation of existing parking spaces to
support a full parking management program. Accessibility features for elderly
and disabled persons will be analyzed to determine if improvements can be
made. A secondary accessway from the Berrellesa crossing to the north will be
included as will minor operational improvements to the Berrellesa crossing.
Action Requested
The City is seeking the cooperation of other affected local agencies as well
as the State to begin to analyze possible solutions to the parking deficiency.
Funding for an Environmental Impact Report (EIR) pursuant to the California
Environmental Quality Act (CEQA) , 1970, as amended, and subsequent project
construction, as appropriate, is proposed. Funds will be sought from local
sources as- well as Section 99622(c) of Proposition 116 approved by the voters
in December 1990.
The City intends to submit an application to Caltrans and the California
Transportation Commission for Proposition 116 Rail Bond funding. In addition
to requests for endorsement of the application, the City is seeking to
establish financial partnerships. with other local agencies and organizations
to support this request. Contributions may take the form of no cost use of
land for project alternatives as well as dollars. Direct financial contribu-
tions may be phased to meet the needs of the contributing entity. Partial
contributions are being sought to support the environmental assessment process
targeting to begin in FY 91/92.
C:mtxprop