HomeMy WebLinkAboutMINUTES - 11271990 - 1.45 TO: BOARD OF SUPERVISORS FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR DATE: November 27, 1990 SUBJECT: DISCOVERY BAY PUMP STATION "G" MODIFICATIONS, DISCOVERY BAY AREA. Project No.: 19.9045 - SPECIFIC REQUEST(S) OR RECOMMENDATION(S) &BACKGROUND AND JUSTIFICATION I. Recommended Action: Award the Contract for furnishing labor and materials for the subject project to William G. McCullough, the low bidder, in the amount of $67,215.50 and at the unit prices submitted; and REQUIRE the contractor to present surety bonds for Payment and Faithful Performance in the amounts of $67,215.50 and $67,215.50, respectively. DIRECT the Public Works Director to prepare the contract for the project. AUTHORIZE the Public Works Director to sign the contract on behalf of the Board subject to the Director having reviewed and found sufficient all required documents, including the contract signed by the contractor, the aforementioned surety bonds, and a certificate of insurance. DIRECT that, in accordance with the project specifications and/or upon the execution of the contract by the Public Works Director, any bid bonds posted by the bidders be exonerated and any checks or cash submitted for bid security be returned. II. Financial Impact: The project, including engineering and appropriate overhead charges is funded by Sanitation District 19. Continued on Attachment: x SIGNATURE: _ RECOMMENDATION OF COUNTY ADMINISTRATOR _ RECOMMENDATION OF BOARD COMMITTEE APPROVE OTHER SIGNATURE(S): ACTION OF BOARD ON N U V 2 7 1990 APPROVED AS RECOMMENDED OTHER _ VOTE OF SUPERVISORS ✓ UNANIMOUS (ABSENT ) AYES: NOES: ABSENT: ABSTAIN: FL:mg c:B027a.tl 1 1 hereby certify that this Is a tree and correct copy of Orig. Div: Public Works (E/S) an action taken and entered on the minutes of the cc: Construction Board of supe on shown. County Administration ATTESTED: "1 2 1990 PHIL BATCHELOR,Cierk of the Board Auditor-Controller of Supervisors and County Administrator Design Accounting By Deputy Contractor Discovery Bay Pump Station November 16, 1990 Page Two III. Reasons for Recommendations and Background: The plans and specifications were approved and the project advertised for bids by the Board of Supervisors on August 21, 1990. The bids were received and opened at Delta Diablo Sanitation District, 2500 Pittsburg-Antioch Highway,Antioch, California, on Thursday, September 27, 1990. The construction bids received were as follows: 1. La Grow Corporation $140,300.00 2. William G. McCullough Company $67,215.50 3. Pacific Mechanical Corporation $84,600.00 The Engineer's estimated construction cost was $58,000.00. IV. Consequences of Negative Action: Failure of existing Pump Station "G" resulting in raw sewage overflow. t