HomeMy WebLinkAboutMINUTES - 02271990 - 1.3 -_n:• -_ 3
TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: February 27, 1990
SUBJECT: PROGRAM SUPPLEMENT #75 WHICH PROVIDES FEDERAL HAZARDOUS
ELIMINATION AND SAFETY (HES) FUNDING FOR PRELIMINARY
ENGINEERING, CONSTRUCTION AND CONSTRUCTION ENGINEERING
FOR THE MEDIAN BARRIER PROJECT ON PLEASANT HILL ROAD AT
TAYLOR BLVD. (PROJECT NO. 0662-6R2548)
Specific Request(s) or Recommendation•(s) & Background &
Justification
I. RECOMMENDATION
Approve and authorize the Chairman of the Board of Supervisors to
execute Program Supplement #75 which provides $180, 000 in
Hazardous Elimination and Safety (HES) funds for preliminary
engineering, construction and construction engineering for the
median barrier project on Pleasant Hill Road at Taylor Boulevard.
II. FINANCIAL IMPACT
The supplement provides reimbursement from HES funds for 90
percent of the County' s estimated costs for the project. The
remaining 10 percent of the funding for these items will come
from County Road Funds.
III. REASONS FOR RECOMMENDATION/BACKGROUND
On June 21, 1977, the Board approved County-State Master
Agreement No. 04-5928 for the funding of Federal Aid Projects.
On August 4, 1987 Contra Costa County qualified for Federal funds
to replace and lengthen the median barrier on Pleasant Hill Road
at Taylor Boulevard.
Continued on attachment: X yes Signature:
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other:
Signature(s) :
Action of Board on: February 27, 1990.
Approved as Recommended X Other
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS
A TRUE AND CORRECT COPY OF AN
X Unanimous (Absent ) ACTION TAKEN AND ENTERED ON
Ayes: Noes: THE MINUTES OF THE BOARD OF
Absent: Abstain: SUPERVISORS ON DATE SHOWN.
Attested February 27, 1990
Orig. Div. :Public Works (RE) PHIL BATCHELOR,
cc: R. Gilchrist, Accounting (PW) CLERK OF THE BOARD
OF SUPERVISORS AND
COUNTY ADMINISTRATOR
KE:md
BO: 2 7 .t 2 By
DEPUTY CLERK
Board of Supervisors
February 27, 1990
Page Two
Caltrans and the Federal Highway Administration have determined
that this County can be reimbursed for the: County' s estimated
Preliminary Engineering , Construction and Construction
Engineering costs for the project.
The County Transportation Committee reviewed this item on
February 13 , 1990.
IV. CONSEOUENCES OF NEGATIVE ACTION
If this program supplement is not approved, the County will have
to absorb the entire cost of Preliminary Engineering,
Construction and Construction Engineering for this project.