HomeMy WebLinkAboutMINUTES - 02271990 - 1.28 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: February 27, 1990
SUBJECT: APPROVE Contract Change Order No. 6 For The Drainage Area 56, Line
Z Project No. 7566-6D8443-87 in the Oakley Area.
Specific Request(s) or Recommendation(s) & Background & Justification
RECOMMENDED ACTION:
APPROVE Contract Change Order No. 6 and AUTHORIZE the Chief Engineer to
execute Contract Change Order No. 6 in the Approximate Amount of $350 to
compensate the contractor, Holman D. Pettibone, Inc. For Increases in
Contract work.
FINANCIAL IMPACT:
The project is funded by Drainage Area 56, Contra Costa County Flood Control
and Water Conservation District.
REASONS FOR RECOMMENDATION/BACKGROUND:
This is a Balancing Contract Change Order to compensate the contractor for
quantities actually installed. Change Order No. 6 and previously Approved
Change Orders collectively exceed $25, 000. 00, which Requires Board Approval .
CONSEQUENCES OF NEGATIVE ACTION:
The Lack of Approval would preclude Payment for work required to complete
this project.
Continued on attachment: yes Signature:
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other:
Signature(s) :
Action of Board on:
Approved as Recommended x— Other
1 hereby certify that this Is a im and correct copy of
an action taken and entered on the minutes of the
Board of Supervisors on the�date �O
shown.
ATTESTED: FEB �2 1990 JJ
PHIL BATCHELOR,Cierk of the Moard
off,Supervisors and CAoountAv Administrator
__ l7ifA Y rwAw !/�iWAJ1i -.Deputy
Vote of Supervisors
X Unanimous (Absent ) ',
Noes: -
Absent: Abstain:
Orig. Div. : PW (Constr)
cc: ' County Administrator
Auditor-Controller
Public Works-Design
Accounting
R. Bruno
Contractor
DG/tt
A:DA56Z27.T2