TO: BOARD OF SUPERVISORS
FROM: Supervisor Tom Torlakson
DATE: November 6, 1990
SUBJECT: APPROVE REQUEST BY THE CITY OF BRENTWOOD AND T & S CONSTRUCTION
COMPANY TO EXTEND THE PERMIT FOR THE CLOSURE OF SUNSET ROAD FOR
THE BRENTWOOD WEST SANITARY INTERCEPTOR CONSTRUCTION PROJECT
SPECIFIC REQUEST(S) OR RECOMMENDATIONS) &BACKGROUND AND JUSTIFICATION
RECOMMENDED ACTION:
Approve a request by the City of Brentwood and T & S Construction Company to.extend the
permit for the closure of Sunset Road to December 15, 1990 to complete the Brentwood West
Sanitary Interceptor Constrution Project. The current permit expires on November 8, 1990.
Direct the Public Works Department to initiate procedures to extend this road closure permit.
BACKGROUND INFORMATION:
Please refer to the attached letters from Donald L. Russell, Brentwood City Manager, and
Michael Hogan of T & S Construction Company.
TT:gro:mg
Attachments
Continued on Attachment: SIGNATURE:
_ RECOMMENDATION OF COUNTY ADMINISTRATOR
_ RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON IVUV b ISqU APPROVED AS RECOMMENDED OTHER
VOTE OF SUPERVISORS
UNANIMOUS (ABSENT )
AYES: NOES:
ABSENT: ABSTAIN: I hereby certify that*.Is is a nue and correct copy of
an action taken ano entered on the rrminutew of the
Board of Supervisors on the date shown.
ATTESTED:
PHIL BATCHELOR,Clerk of the Board
Of Supervisors and county AdminiAtrator
cc: Distribution via P.W.
City of Brentwood ""•�p'n''
T & S Construction
E. King, Permit Engineer
J
a
JpR a
i;....Xtt tL'•g4,- .+....i...:R?L. e. .!5.:..lt4wt" tl:'.....•.Ic•.w.`.^,.. :...SV'¢ �+ .... ,
November 5, 1990
Mr. Tom Torlakson, Supervisor
Contra Costa County Board of Supervisors
300 East Leland Road, Suite 100
Pittsburg, CA 94565
SUBJECT: West Sanitary Interceptor Project
Dear Supervisor Torlakson:
We respectfully request and urge your assistance in securing a road closure permit extension for
Sunset Road in Brentwood regarding the above-mentioned project. The current permit allows for
closure until November 6, 1990,
T & S Construction Company has experienced: very slow progress. They now anticipate that the
work on Sunset Road will not be completed until December 15, 1990.
As the road closure permit expires on November 6, 1990, I am requesting that this issue be placed
on the Board Agenda for the November 6, 1990, meeting allowing until December 15, 1990, to
complete the work on Sunset Road.
Sincerely,
Cl"
RE OOD
Dussell
City Manager
DLR/DWB/jmp
CONSTRUCTION CO., INC
6108 HEDGE AVENUE
SACRAMENTO, CA 95829
PHONE 616-381-3052
November 1, 1950
Contra Costa County
Supervisor Torlak.son-District 5 r
255 Glacier Drive
Martinez, Ca. X14553
Attn: Sharon Creswell
Re: Road Closure Permit No. 8361-6113 for Sunset Rond
Dear Ms. Creswi!ll:
You and Contra Costa County Public works Department staff are aware
of the Brentwood West Sanitary Interceptor Project and the extremely dan-
gerous and dif!'icult conditions encountered during its construction.
Staff from the City of Brentwood, the Contra Costa County Department of
Public Works, :tnd T & S Construction have met several times durJn con-
struction of the project. r
The last m+seting between these parties to discuss the referenced s
f
permit was held September 28, 1990. As a result of that meeting, an ex-
tension of the road closure permit until November 8, 1990 was granted.
T & S Construc :ion openly admitted to all parties at that time that this
extension may -tot be adequate due to the difficult consttuction• being
encountered on Sunset Road. We felt that our request, for an extension
was reasonable in light of tbo information available, and our desire to
make a request which was endorsed by all parties concerned.
Since that meeting, T & S Construction has been working dawn to
dusk, six day's a week in an all out effort to complete work on Sunset
Road as soon as possible. Indeed, we have made significant progress. Of
the 1 ,000 feet yet to be constructed a month ago, 460 feet now remain.
This letter is our final request for a permit extension. The pro-
duction rates achieved in the last month allow us to make an accurate
estimation of the time required to complete our work on Sunset Road.
T b 8 construction can now guarantee that pipeline work on Sunset Road
will be complete on-or before December 15, 1990.
The closure of Sunset Road has become a necessity due to the un-
stable soils and utilities that exist. Due to a conflict with a P. C.
& E. gas tine the sewer pipeline has been shifted to the road center-
line by the City of Brentwood. Because of the unstable soils and the
numerous utilities which exist, T & S Construction is using steel
sheat pits shoring for the excavation. These factors make it impos-
sible to complete our work while the road is open ,and assure *pbldli.c
safety. As always, we will continua to make provisions for emergency
vehicles if our request is granted.
We regret the inconvenience inflicted upon your constituent$ by
this construction activity. This inconvenience is an unfortunate con-
sequence of underground construction within the public right of way
and is beyond the control of T & S Construction. We have worked
closely on a personal level with many of the residents along Sunset
Road to mitigate construction impacts.
Thank you for considering our request. I can be reached at (316)
381-3057 if you would like to discuss this issue or i can provide
more information.
Respectfully Submitted,
Michael Hogan
T 8 8 Construction Co., Inc.