HomeMy WebLinkAboutMINUTES - 11061990 - 1.4 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: November 6, 1990
SUBJECT: Increase in Contingency Fund for the 1990 Handicap Ramp Project,
Project No. 0662-6R4033-90
Specific Request(s)or Roommn ndadion(a)&Background&Justification
RECOMMENDED ACTION:
APPROVE Contingency Fund increase of $7,000.00 to compensate the contractor, Whiteside
Construction, for contract item increases.
FINANCIAL IMPACT:
The increase in the contingency fund will be funded by a Community Development Block Grant.
REASONS FOR RECOMMENDATION/BACKGROUND:
The bulk of the additional money is needed to pay the contractor for the placement of 12.5 cubic yards
of additional concrete, not contemplated by the original plan.
CONSEQUENCES OF NEGATIVE ACTION:
The lack of APPROVAL would preclude the payment to the contractor for work required for the
successful completion of the contract.
Continued on attachment: _yes SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON: NOV 6 1990 APPROVED AS RECOMMENDED k1o" OTHER
VOTE OF SUPERVISORS
V' UNANIMOUS(ABSENT___j
ABSENT: ABSTAIN:
1 he+ehy c*rtiy that this is a mie end correct copy of
Orig. Div.: PW(Constr) an action taken and entered on the minutes of the
cc: County Administrator Board of Supervisors on the date shown.
Auditor-Controller ATTESTED: N ny R 1ggn _
PHIL BATCHELOR,Clerk of the Board
Public Works - Design etsupwvw=and cow►
R. Bruno ,
Contractor �r ��' '"�" —d .oso ►
KE:tt
c:BO\RHR-6.t11