HomeMy WebLinkAboutMINUTES - 11281989 - 1.5 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: November 28, 1989
SUBJECT: PROGRAM SUPPLEMENT #74 WHICH PROVIDES FEDERAL AID
SECONDARY (FAS) FUNDING FOR CONSTRUCTION ENGINEERING AND
CONSTRUCTION FOR THE ROAD WIDENING PROJECT ON LONE TREE WAY., SR4
TO ANTIOCH CITY LIMITS (PROJECT NO. 0662-6M40I0)
Specific Request(s) or Recommendation(s) & Background &
Justification
I. RECOMMENDATION
APPROVE and authorize the Chairman of the Board of Supervisors to
execute Program Supplement #74 which provides $529, 817 in Federal
Aid Secondary (FAS) funds for Construction Engineering and
Construction for the road widening project on Lone Tree Way,
State Route 4 to the Antioch City limits.
II. FINANCIAL IMPACT
The supplement provides reimbursement from FAS funds for 86
percent of the County's estimated costs for the project. The
County must provide the remaining 14 percent of the funding for
these items.
III. REASONS FOR RECOMMENDATION/BACKGROUND
On June 21, 1977 , the Board approved County-State Master
Agreement No. 04-5928 for the funding of Federal Aid Projects.
This project is scheduled to be advertised for contract bids in
Winter 1990. Construction is expected to be completed by Spring
1990.
Continued on attachment: X yes Signature: fuf�l_ .
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other:
Signature(s) :
Action of Board on: NOV 2 8 1989
Approved as Recommended ✓ Other
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS
A TRUE AND CORRECT COPY OF AN
Unanimous (Absent ) ACTION TAKEN AND ENTERED ON
Ayes: Noes: THE MINUTES OF THE BOARD OF
Absent: Abstain: SUPERVISORS ON DATE SHOWN.
Attested NOV 2 8 1989
Orig. Div. : Public Works (RE) PHIL BATCHELOR,
cc: R. Gilchrist, Accounting CLERK OF THE BOARD
OF SUPERVISORS AND
COUNTY ADMINISTRATOR
JMW:KE:sd
BO: 28.t11
DEPUTY CLERK
Board of Supervisors
November 28, 1989
Page 2
III. REASONS FOR RECOMMENDATION/BACKGROUND (continued)
Caltrans and the Federal Highway Administration have determined
that this County can be reimbursed for the County's estimated
Construction Engineering and Construction costs for the project.
The County Transportation Committee reviewed this item on
November 14 , 1989 .
IV. CONSEQUENCES OF NEGATIVE ACTION
If this program supplement is not approved, the County will have
to absorb the entire cost of Construction Engineering and
Construction for this project.