TO: BOARD OF SUPERVISORS, AS GOVERNING BOARD OF CONTRA
COSTA COUNTY FLOOD CONTROL AND WATER CONSERVATION
DISTRICT
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: November 29, 1988
SUBJECT: Request to Place Wildcat-San Pablo Creeks Project Under
New State Subvention Criteria Established by Senate
Bill No. 502 , North Richmond
Specific Request(s) or Recommendation(s) & Background &
Justification
I. RECOMMENDATION
AUTHORIZE the Chief Engineer to send a letter to the State
Department of Water Resources indicating that the Contra Costa
County Flood Control and Water Conservation District elects to
have the Wildcat-San Pablo Creeks Corps of Engineers Project
placed under the new State of California subvention criteria
established by Senate Bill No. 502 .
II. FINANCIAL IMPACT
The State of California ' s participation in the project will
increase by approximately $900, 000.
Continued on attachment: X yes Signature:
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other:
Signature(s)
-
Action :of Board on: NOV 2 9 1988
Approved as Recommended_ Other
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS
A TRUE AND CORRECT COPY OF AN
Unanimous (Absent ) ACTION TAKEN AND ENTERED ON
Ayes: Noes: THE MINUTES OF THE BOARD OF
Absent: Abstain: SUPERVISORS ON DATE SHOWN.
Attested NOV 2 9 1988
Orig. Div. :Public Works (FCE) PHIL BATCHELOR,
cc: County Administrator CLERK OF THE BOARD
County Counsel OF SUPERVISORS AND
Public Works Dept: COUNTY ADMINISTRATOR
Accounting
Flood Control Eng.
Design
MFK:md
B0: 9a.t11 11&,
By
DEPUTY CLERK
1 ,
31
III. REASONS FOR RECOMMENDATION/BACKGROUND
The State of California has adopted legislation to make the State
Department of Water Resources Subvention Program Guidelines
compatible with the new federal cost sharing regulations passed
by Congress for all Federal Flood Control Projects. The revised
state guidelines establish a 70% reimbursement on all non-federal
project cost including the mandatory 5% cash contribution by the
local sponsor.
The project financing report presented to the Board on April 26,
1988 indicated that the revised guidelines would increase the
State participation by $900, 000 thereby cutting the project
deficit from $1, 800, 000 to $900, 000.
IV. CONSEQUENCES OF NEGATIVE ACTION
Our local cost share will be greater under the old guidelines.