HomeMy WebLinkAboutMINUTES - 11011988 - 1.12 TO: BOARD OF SUPERVISORS, AS THE GOVERNING BODY OF FLOOD
CONTROL
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: November 1, 1988
SUBJECT: APPROVE Contract Change Order #2 for Drainage Area 56,
Lindsey Basin, Project #7566-6D8462-86, W.O. #8462 , in
the Oakley area.
Specific Request(s) or Recommendation(s) & Background &
Justification
RECOMffiWDED ACTION.
APPROVE Contract Change Order No. 2 in the amount of $96, 000 and,
AUTHORIZE the Chief Engineer to execute it in order to compensate
the contractor Oliver- de Silva, Inc. for work resulting from
design changes.
FINANCIAL IMPACT:
The existing contingency fund is sufficient to cover this increase
in cost.
REASONS FOR RECOMMENDATION/BACKGROUND:
This change order relocates an irrigation line in conflict,
modifies a bridge guardrail, and abandons a well.
This change order and a previously approved change order
collectively exceed $25, 000 and Board approval is required.
CONSEQUENCES OF NEGATIVE ACTION:
Lack of approval would preclude payment to the contractor for
required work and prevent successful completion of the project.
Continued on attachment: yes Signature///
laarcc,�
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other:
Si ature s :
Action of Board on: NOV 1 19- 89
Approved as Recommended Other
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS A TRUE
AND CORRECT COPY OF AN ACTION TAKEN
__X _Unanimous(Absent ) AND ENTERED ON THE MINUTES OF THE
Ayes: Noes: BOARD OF SUPERVISORS ON DATE SHOWN.
Absent: Abstain:
Attested NOV 1 1988
Orig. Div. : PW(Constr) Phil Batchelor
cc: County Administrator Clerk of the Board of
Auditor-Controller Supervisors and County
Design Administrator
PW Accounting
Contractor
Qn ,
BJK/GB/sa By /�A.Crnllse , DEPUTY
bo: 1.tll