HomeMy WebLinkAboutMINUTES - 10111988 - 1.4 r
TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: October 11, 1988
SUBJECT: Property Acquisition, Appian Way Widening Phase II, E1
Sobrante Area
Project No. : 0662-6R4288 Task: ACQ Account: 3540
SPECIFIC REQUEST(S) OR RECOMMENDATION(S) & BACKGROUND AND
JUSTIFICATION
I. Recommended Action:
APPROVE Right of Way Contracts and ACCEPT Deeds listed below:
GRANTOR DOCUMENT DATE PAYEE AMOUNT
Wellington Chang Grant Deed 05/24/88 Wellington Chang $550.00
You-Lien Chang Right of Way 10/11/88 You-Lien Chang
Jerry Chang Contract Jerry Chang
Andy Chang Andy Chang
Bing Yiu Mak Grant Deed 01/25/88 Bing Yiu Mak $550.00
Sze Lee Mak Right of Way 10/11/88 Sze Lee Mak
Contract
Kit Man Ming Grant Deed 06/22/88 Kit Man Ming $550.00
Pui Ying Ming Right of Way 10/11/88 Pui Ying Ming
Contract
Cont'd on Attachment: X yes Signature:
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other
Signature(s)
Action of Board on
Approved as recommended li Other
Vote of Supervisors
✓ Unanimous (Absent ) I HEREBY CERTIFY THAT THIS
Ayes: Noes: IS A TRUE AND CORRECT COPY
Absent: Abstain: OF AN ACTION TAKEN AND
ENTERED ON THE MINUTES OF
THE BOARD OF SUPERVISORS ON
DATE SHOWN.
ATTESTED OCT 111968
PHIL BATCHELOR, Clerk of
the Board of Supervisors
and County Administrator
BY
DEPUTY
Orig. Div: Public Works (R/P)
cc: County Administrator
Auditor-Controller (via R/P)
P. W. Accounting
Recorder (via R/P)
A
AUTHORIZE Public Works Director to execute said Right of Way
Contracts on behalf of the County.
APPROVE payments as listed above for said property rights
and AUTHORIZE the Auditor-Controller to issue checks in said
amounts payable to the listed payees, to be forwarded to the
Real Property Division for delivery.
DIRECT the Real Property Division to have the above
referenced Grant Deeds recorded in the office of the County
Recorder.
II. Financial Impact:
Payment of $1,650.00 from the aforementioned contracts will
come from Appian Way Phase II road widening funds which are
86% reimbursable from Federal Highway Administration.
III. Reasons for Recommendations:
These property rights are required for the Appian Way Phase
II road widening project in accordance with approved plans
and specifications.
IV. Consequences of Negative Action:
The project will not have sufficient land rights to allow
construction in accordance with the approved plans and
specifications.
GK:rs
BO:1211.t10