TO: BOARD OF SUPERVISORS
FRCK: J. MICHAEL WALFIORD, PUBLIC WORDS DIRE=R
DATE: January 12, 1988
SUBJECT: Increase Contingency Fund and Authorize Contract Change Order No. 2 for
the 1987 Guardrail Replacement Project, Project No. 0672-61J2530-86, in
the Crockett Area.
Specific Request(s) or Rec umendation(s) & Background & Justification
REOOMMENEE'.D ACTION:
APPRJVE Contingency Fund Increase of $1,000.00 and AUTHMIZE the Public Works
Director to execute Contract Change Order No. 2 to balance the Contract Items for
the 1987 Guardrail Replacement Project, Project No. 0672-6U2530-86, in the Crockett
area.
FINANCIAL IMACT•
The project is funded by County road funds.
REASONS Fit ON/BAC[GR0LIND•
The additional money is needed to pay the Contractor for work that was required
to conplete the contract.
O )ENCES OF NEGATIVE ACTION:
The lack of approval would preclude the payment for work done by the contractor.
Continued on attacbuiettt: yes Signa --
Recmu endation of County Administrator tion of 6oard 'ttee
Approve Other:
Signature(s)
Action of .Board on: JAN 12 1988 Approved as wed X other
Vote of Supervisors I MZMY C WM THAT THIS IS A TRUE
AND C RUIECT DOPY OF AN ACTION TAFEN
X Unanimous (Absent ) AND ERIT RID ON THE NIINUI!'S OF THE
Ayes: Noes: BOARD OF S[JPE RISORS ON DATE SHOM.
Absent: Abstain: Attested JAN 12 X988
Orig. Div.: Public Works (Construction) ;Phil Batchelor
cc: County Administrator Clerk of the Board of
Auditor-Controller Supervisors and County
Design Administrator
st-rator
PW Accounting
Contractors
By . DEp[TI'Y
BJK/KC/sa
bo:12.t1