HomeMy WebLinkAboutMINUTES - 02021988 - 1.1 A
TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
.DATE: February 2 , 1988
SUBJECT: Property Acquisition, Appian Way Widening Phase II ,
El Sobrante Area
Project No. : 0662-6R4288 Task: ACQ Account: 3540
SPECIFIC REQUEST(S) OR RECOMMENDATION(S) & BACKGROUND AND
JUSTIFICATION
I. Recommended Action:
APPROVE Right of Way Contracts and ACCEPT Deeds listed below:
GRANTOR DOCUMENT DATE PAYEE AMOUNT
Houshang Tom Taleb Grant Deed 12/28/87 First American $2 , 400 . 00
Ghodsie S. Talebi Right of Way 02/02/88 Title Guaranty
Contract Company, Escrow
No. 752435
Daniel Bumgardner Grant Deed 12/26/87 First American $1, 200. 00
Ginger Bumgardner Right of Way 02/02/88 Title Guaranty
Contract Company, Escrow
No. 752453
Continued on Attachment: X yes Signature:
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other
Signature(s)
Action of Board on FEB 4 1988
Approved as recommended _X_— Other
Vote of Supervisors
X Unanimous (Absent ) I HEREBY CERTIFY THAT THIS
Ayes: Noes: IS A TRUE AND CORRECT COPY
Absent: Abstain: OF AN ACTION TAKEN AND
ENTERED ON THE MINUTES OF
THE BOARD OF SUPERVISORS ON
DATE SHOWN.
ATTESTED FEB 4 1989
PHIL BATCHELOR, Clerk of
the Board of Supervisors
and County Administrator
BY
DEPUTY
Orig. Div: Public Works (R/P)
cc: County Administrator
Auditor-Controller (via R/P)
P. W. Accounting
Recorder (via R/P)
a
AUTHORIZE Public Works Director to execute said Right of Way
Contracts on behalf of the County.
APPROVE payments as listed above for said property rights and
AUTHORIZE the Auditor-Controller to issue checks in said
amounts payable to the listed payees, to be forwarded to the
Real Property Division for delivery.
DIRECT the Real Property Division to have the above
referenced Grant Deeds recorded in the office of the County
Recorder.
II. Financial Impact:
Payment totalling $3 , 600. 00 for the aforementioned contracts
will come from Appian Way Phase II road widening funds which
are 86% reimbursable from Federal Highway Administration.
III. Reasons for Recommendations/Background:
These property rights are required for the Appian Way Phase
II road widening project in accordance with approved plans
and specifications.
V. Consequences of Negative Action:
The project will not have sufficient land rights to allow
construction in accordance with the approved plans and
specifications.
GK:rs
BO: 12awII26.tl
TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: February 2 , 1988
SUBJECT: Property Acquisition, Appian Way Widening Phase II,
El Sobrante Area
Project No. : 0662-6R4288 Task: ACQ Account: 3540
SPECIFIC REQUEST(S) OR RECOMMENDATIONS) & BACKGROUND AND
JUSTIFICATION
I. Recommended Action:
APPROVE Right of Way Contracts and ACCEPT Deeds listed below:
GRANTOR DOCUMENT DATE PAYEE AMOUNT
Paul H. Kim Grant Deed 01/04/88 First American $2 , 400. 00
Kelly Z . Kim Right of Way 02/02/88 Title Guaranty
Contract Company, Escrow
No. 752436
Roy J. Johnson Grant Deed 01/04/88 Founders Title $4 , 800. 00
Bernelle Johnson Right of Way . 02/02/88 Company, Escrow
Contract No. 871172
Roelfina Prins Grant Deed 01/02/88 First American $3 , 000. 00
Right of Way 02/02/88 Title Guaranty
Contract Company, Escrow
No. 752419
Cont'd on Attachment:_ X yes Signature: 9A
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other
Signature(s)
Action of Board on
Approved as recommended X Other
i
Vote of Supervisors
X Unanimous (Absent ) I HEREBY CERTIFY THAT THIS
Ayes: Noes: IS A TRUE AND CORRECT COPY
Absent: Abstain: OF AN ACTION TAKEN AND
ENTERED ON THE MINUTES OF
THE BOARD OF SUPERVISORS ON
DATE SHOWN.
ATTESTED FEB 2 1988
PHIL BATCHELOR, Clerk of
the Board of Supervisors
and County Administrator
BY 4rcZA
e - )_�L_
DEPUTY
Orig. Div: Public Works (R/P)
cc: County Administrator
Auditor-Controller (via R/P)
P. W. Accounting
Recorder (via R/P)
l r
AUTHORIZE Public Works Director to execute said Right of Way
Contracts on behalf of the County.
APPROVE payments as listed above for said property rights and
AUTHORIZE the Auditor-Controller to issue checks in said
amounts payable to the listed payees, to be forwarded to the
Real Property Division for delivery.
DIRECT the Real Property Division to have the above
referenced Grant Deeds recorded in the office of the County
Recorder.
II. Financial Impact:
Payment totalling $10, 200. 00 for the aforementioned contracts
will come from Appian Way Phase II road widening funds which
are 86% reimbursable from Federal Highway Administration.
III. Reasons for Recommendations/Background:
These property rights are required for the Appian Way Phase
II road widening project in accordance with approved plans
and specifications.
V. Consequences of Negative Action:
The project will not have sufficient land rights to allow
construction in accordance with the approved plans and
specifications.
GK:rs
BO: 12awII2 .t2