Loading...
HomeMy WebLinkAboutMINUTES - 11031987 - 1.12 2- TO: TO: BOARD OF SUPERVISORS FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR DATE: November 3, 1987 SUBJECT: Increase in Contingency Fund and Approval of Contract Change Order No. 4 for the East Bates Avenue Assessment District project in Concord. Specific Requests or Recommendations & Background & Justification RECOMMENDED ACTION: APPROVE Contingency Fund increase of $42 ,395.07 and AUTHORIZE the Public Works Director to execute Contract Change Order No. 4 in the amount of $47,129.33 to compensate the Contractor, Gallagher & Burk, Inc. , for additional work due to design changes. FINANCIAL IMPACT: The increase in the Contingency Fund wi l l be funded by the East Bay Municipal Utility District, $33,126.50, and by the A.J. Seeno Company, $9,268.57 for improvements not included in the Assessment District scope of work. REASONS FOR RECOMMENDATION/BACKGROUND: Work unforseen on the original plans was necessary to fulfill an easement requirement with EBMUD and the development of the Seeno Company property. CONSEQUENCES OF NEGATIVE ACTION: The lack of approval precludes payment to the Contractor for work necessary for the successful completion of the project. Continued on attachment: yes Signature: Recommendation of County Administrator Recommendation Board omni ee Approve Other: Signature(s): Action of Board on: N O V 3 1987 Approved as Recommended_ Other Vote of Supervisors I HEREBY CERTIFY: THAT THIS IS A TRUE AND CORRECT COPY OF AN ACTION TAKEN Unanimous (Absent ) AND ENTERED ON THE MINUTES OF THE Ayes: Noes: BOARD OF SUPERVISORS ON DATE SHOWN. Absent: Abstain: Attested NOV 3 1987 Orig. Div.: Public Works (Construction) Phil Batchelor cc: County Administrator 'Clerk-of-the Board of Auditor-Controller Supervisors and County Design Administrator PW Accounting Contractor BJK/KC:sa By DEPUTY bo:3.tll