HomeMy WebLinkAboutMINUTES - 01201987 - 1.5 (3) File: 250-8639/B.4
THE BOARD OF SUPERVISORS
CONTRA COSTA COUNTY, CALIFORNIA
Adopted this Order on January 20, 1987, by the following vote:
AYES: Supervisors Powers , Fanden, Torlakson and McPeak
NOES: None
ABSENT: Supervisor Schroder
SUBJECT: Award of Contract for
Building Alterations and Site Improvements
at 255 Glacier Drive for
Public Works Department
Martinez
Budget Line Item No. 4425-4241
Authorization No. 0928-WH241B
BIDDER TOTAL AMOUNT Bond Amounts
Malpass Construction Co. , Inc. $242,500 Base Labor & Materials $121,250
503 Waterberry Drive Bid Only Faithful Performance $242,500
Pleasant Hill , California 94523
TJ Construction Co. , Inc.
Moraga, California
M-3 Construction
Sacramento, California
Arthur Bros. , Inc.
San Mateo, California
West Coast Contractors, Inc.
Fairfield, California
Vitton Construction Co. Inc.
Castro Valley, California
Tyler Construction, Inc.
Antioch, California
The above-captioned project and the specifications therefor being approved,
Addendum No. 1 being issued and bids' being duly invited and received by the
Director of General Services; and
The Director of General Services recommending that the bid listed first
above is the lowest responsible bid and this Board concurring and so finding;
IT IS BY THE BOARD ORDERED that the contract for the furnishing of labor
and materials for said work is awarded to said first listed bidder at the
listed amount and at the prices submitted in said bid; and that said
contractor shall present two good and sufficient surety bonds as indicated
above; and that the General Services Department shall prepare the contract
therefor; and
Page 1 of 2
IT IS FURTHER ORDERED that after the contractor has signed the contract
and returned it, together with bonds as noted above and any required
certificates of insurance or other required documents, and the Director of
General Services has reviewed and found them to be sufficient, the Director of
General Services is authorized to sign the contract for this Board; and
IT IS FURTHER ORDERED that in accordance with the project specifications
and/or upon signature of the contract by the .Director of General Services,
any bid bonds posted by the bidders are to be exonerated and any checks or
cash submitted for bid security shall be returned.
1 her2h3 CCrttfy that this is a true and correct copy of
an ac-11on F viivi5 and entered on the minutes of the•
BOM'.. c: on the date shown.
AT JAN 2 019$7
Pi i?i_ PEAS 6 C ei"-LOR, CkE.' of Cia,D-rowd
Of .C;UPC. is rs mild County�'td.iJntstrc?tQf
By .Lh�__)1L � Deputy
� y
Orig. Dept. General Services Dept. - Architectural Div.
cc: General Services Department
Architectural Division
G.S. Accounting
Auditor-Controller
Public Works Accounting
Contractor (Via A.D. )
25039B01.16A