HomeMy WebLinkAboutMINUTES - 01061987 - 1.21 4
TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: January 6, 1987
SUBJECT: Approve Prior Issuance of Addendum No. 1 to the Notice and Proposal
for Lane Drive Sewer Extension, Project No. 1520-6B-8622
Specific Requests or Recommendations & Background & Justification
RECOMMENDED ACTION:
The Public Works Director as ex officio the Chief Engineer of the Contra Costa County Flood
Control and Water Conservation District has recommended approval of the prior issuance of
an addendum to the Notice and Proposal for the Lane Drive Sewer Extension project.
FINANCIAL IMPACT:
The Addendum. increases the project costs by approximately $6,000.
REASONS FOR RECOMNENDATION/BACKGROUND:
The contract provides for connection of existing house septic tank systems adjacent to Pine
Creek to new sewer facilities. An increase in the quantities of pipe and fittings is
necessary in order to install the sewer lateralsin a manner acceptable to the property
owners. Also, special construction methods (pipe jacking) can be eliminated over a portion
of the work by adding a contract item and a related special provision section. The Addendum
will result in a net increase in project cost 'of approximately $6 ,000.
CONSEQUENCES OF NEGATIVE" ACTION:
The contract cost would be increased approximately $12,000 without i ddendum.
Continued on attachment: yes Signature:
Recommendation of County Administrator Recommen on of r Committee
Approve Other: f
Signature(s) :
Action of Board on: JAN 6 1987 Approved as Recommended Other
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS A TRUE' -
-AND -CORRECT
RUE,AND CORRECT COPY OF AN ACTION TAKEN
Unanimous (Absent ) AND ENTERED ON THE- MINUTES OF THE
Ayes: Noes: BOARD OF SUPERVISORS ON DATE SHOWN,
Absent: Abstain:
Attested JAN 6 1987
Orig. Div.: Public Works - Design -Phil Batchelor
cc: Clerk of the -Board of
,,Supervisors and County
.Administrator
By y DEPUTY
BT:dk
bo:lane6.tl