HomeMy WebLinkAboutMINUTES - 02031987 - 1.7 TO: BOARD OF SUPERVISORS, as the Governing Board of Contra Costa County Flood Control
and Water Conservation District
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: February 3, 1987
SUBJECT: Approve the Issuance of a Purchase Order for Utility Relocations for the Upper
Pine Creek Project, Project No. 7520-6B8689, Concord Area.
Specific Requests or Recommendations & Background & Justification
RECOMMENDED ACTION:
AUTHORIZE the issuance of a purchase order to the Pacific Gas and Electric Company for the
relocation of three gas lines in Concord.
FINANCIAL IMPACT•
The amount of the purchase order is $60,000 which is partially reimbursable by the State
Department of Water Resources.
REASONS FOR RECOMMENDATION/BACKGROUND:
The purchase order provides for the relocation of three gas lines which are in conflict
with the Corps of Engineers' Upper Pine Creek Project. Relocation of the gas lines outside
the construction limits will provide increased safety and ensure continued service to
utility customers during construction.
CONSEQUENCES OF NEGATIVE ACTION:
The gas lines would have to be relocated by the Corps' contractor and would cause struction
delays and increase the construction cost of the Upper Pine Creek Proj
Continued on attachment: yes Signature:
Recommendation of County Administrator Recommend on of B647,116mmittee
Approve Other:
Signature(s):
Action of Board on: FEB 3 1987 Approved as Recommended /,Other
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS A TRUE
AND CORRECT COPY OF AN ACTION TAKEN
Unanimous (Absent ) AND ENTERED ON THE MINUTES OF THE
Ayes: Noes: BOARD OF SUPERVISORS OH DATE SHOWN.
Absent: Abstain: —
Attested FEB 3 1907
Orig. Div.: Public Works (Design) Phil Batchelor
cc: Clerk of the Board of
Supervisors and County
Administrator
By ,,a , , DEPUTY
BT:sj
BO:3.tl