HomeMy WebLinkAboutMINUTES - 02241987 - 1.94 File: 135-8509/B. 4
THE BOARD OF SUPERVISORS
CONTRA COSTA COUNTY, CALIFORNIA
Adopted this Order on February 24, 1987, by the following vote:
AYES: Supervisors Powers , Fanden, Schroder, Torlakson & McPeak
NOES: None
ABSENT: None
SUBJECT: Award of Contract for
Remodeling for Training Room
at 1305 'MacDonald Avenue,
Richmond
Budget Line Item No. 4423-4221
Authorization No. 0928-WH221B
BIDDER TOTAL AMOUNT Bond Amounts
All Phase Builders $27 , 500 which Labor & Materials $13 , 950
732 Leland Way includes Faithful Performance $27, 900
Livermore, CA 94550 $23, 925 Base
Bid and $3 ,975
Add. Alt. No. l
Edward A. Sparacino
General Contractor
Martinez, California
A-1 Plus Construction
San Ramon, California
Tamal Construction Co.
Richmond, California
John M. DeRespini Construction
Pleasant Hill, California
Adonis Allied, Inc.
El Cerrito, California
TJ Construction Co. , Inc.
Moraga, California
The above-captioned project and the specifications therefor
being approved, Addendum No. 1 being issued and bids being duly
invited and received by the Director of General Services; and
The Director of General Services recommending that the bid
listed first above is the lowest responsible bid and this Board
concurring and so finding;
IT IS BY THE BOARD ORDERED that the contract for the furnishing
of labor and materials for said work is awarded to said first
listed bidder at the listed amount and at the prices submitted in
said bid; and that said contractor shall present two good and
sufficient surety bonds as indicated above; and that the General
Services Department shall prepare the contract therefor; and
Page 1 of 2
IT IS FURTHER ORDERED that after the contractor has signed the
contract and returned it, together with bonds as noted above and
any required certificates of insurance or other required documents,
and the Director of General Services has reviewed and found them to
be sufficient, the Director of General Services is authorized to
sign the contract for this Board; and
IT IS FURTHER ORDERED that in accordance with the project
specifications and/or upon signature of the contract by the
Director of General Services, any bid bonds posted by the bidders
are to be exonerated and any checks or cash submitted for bid
security shall be returned.
1 hereby certify that this is a true and correct copy of
an; on taken and v.itisrod on the minutes of the
Board of supervisors on the date shown.
ATTES'i D: . FEB 2 41987
WiL BATCHELOR, C:erk of the Board
of Supervisorc and County Aministrator
By ��h r . Deputy
I
Orig. Dept. General Services Dept. - Architectural Division
cc: General Services Department
Architectural Division
G. S. Accounting
Auditor-Controller
Public Works Accounting
Contractor (Via A.D. )
13509B02. 20A
GB:ml
Page 2 of 2