TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: December 1, 1987
SUBJECT: Approve Contract Change Order #4 for the North Richmond Bridges project.
Project #0662-.6R4333-86, in the north Richmond area.
Specific Requests or Recommendations & Background & Justification
RECOMMENDED ACTION:
APPROVE Contract Change Order #4 in the amount of $4,000 and AUTHORIZE the Public Works
Director to execute it in order to compensate the contractor, C. Overaa & Company, for
grading work needed to protect private property."
FINANCIAL IMPACT:
The project contingency funds are sufficient to cover this change order.
REASONS FOR RECOMMENDATION/BACKGROUND:
This work is needed to protect private property from flooding due to a possible overflow of
San Pablo Creek. The cumulative total of this and previous Contract Change Orders exceeds
$25 ,000, requiring Board approval .
CONSEQUENCES OF NEGATIVE ACTION:
Failure to do this work could result in flooding of private property.
Continued on attachment: _ yes i ature:
Recommendation of County Administrator Recommendation of Board Committee
_ Approve Other:
Signature(s):
Action of Board on: nFt' 1 1987 Approved as Recommended—_ Other
G
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS A TRUE
AND CORRECT COPY OF AN ACTION TAKEN
X Unanimous (Absent ) AND ENTERED ON THE MINUTES OF THE
Ayes: Noes: BOARD OF SUPERVISORS ON DATE SHOWN. _;
Absent: Abstain:
— Attested U 1 1987
Orig. Div.: Public Works (Construction) Phil Batchelor
cc: County Administrator Clerk of the Board of
Auditor-Controller Supervisors and County
Design Administrator
— -
_PW Accounting----
Contractor
ccounting---Contractor
BJK/GB:sa By DEPUTY
bo:1.t12