HomeMy WebLinkAboutMINUTES - 08182015 - C.03RECOMMENDATION(S):
1. APPROVE plans, specifications, and design for the Byron Airport Pavement Enhancements Project, Byron area.
County Project No. 4875-4650-SAS-6X5314/Federal Project No. AIP 03-06-0008-014
2. DETERMINE that the bid submitted by Maxwell Asphalt, Inc. (“Maxwell Asphalt”), exceeded the Disadvantaged
Business Enterprise (DBE) Goal for this project and that Maxwell Asphalt has submitted the lowest responsive and
responsible bid for the base bid plus Alternate No. 1 combined per our specification for the project.
3. APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a construction contract for the
above project with Maxwell Asphalt, in the listed amount ($851,353.48) and the unit prices submitted in the bid and
DIRECT that Maxwell Asphalt shall present two good and sufficient surety bonds as indicated below, and that the
Public Works Director, or designee, shall prepare the contract.
4. ORDER that, after the contractor has signed the contract and returned it, together with the bonds as noted below
and any required certificates of insurance or other required documents, and the Public Works Director has reviewed
and found them to be sufficient, the Public Works Director, or designee, is authorized to sign the contract for this
APPROVE OTHER
RECOMMENDATION OF CNTY
ADMINISTRATOR
RECOMMENDATION OF BOARD
COMMITTEE
Action of Board On: 08/18/2015 APPROVED AS
RECOMMENDED
OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Candace Andersen, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
ABSENT:Federal D. Glover, District V
Supervisor
Contact: Kevin Emigh,
925-313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors
on the date shown.
ATTESTED: August 18, 2015
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: Stacey M. Boyd, Deputy
cc:
C. 3
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:August 18, 2015
Contra
Costa
County
Subject:Construction Contract for the Byron Airport Pavement Enhancements Project, Byron area.
RECOMMENDATION(S): (CONT'D)
Board.
5. ORDER that, in accordance with the project specifications and/or upon signature of the contract by the Public
Works Director, or designee, any bid bonds posted by the bidders are to be exonerated and any checks or cash
submitted for security shall be returned.
6. ORDER that, the Public Works Director, or designee, is authorized to sign any escrow agreements prepared for
this project to permit the direct payment of retentions into escrow or the substitution of securities for moneys
withheld by the County to ensure performance under the contract, pursuant to Public Contract Code Section 22300.
7. DELEGATE, pursuant to Public Contract Code Section 4114, to the Public Works Director, or designee, the
Boards’ functions under Public Contract Code Sections 4107 and 4110.
8. DELEGATE, pursuant to Labor Code Section 6705, to the Public Works Director, or to any registered civil or
structural engineer employed by the County, the authority to accept detailed plans showing the design of shoring,
bracing, sloping, or other provisions to be made for worker protection during trench excavation covered by that
section.
9. DECLARE that, should the award of the contract to Maxwell Asphalt be invalidated for any reason, the Board
would not in any event have awarded the contract to any other bidder, but instead would have exercised its discretion
to reject all of the bids received. Nothing in this Board Order shall prevent the Board from re-awarding the contract to
another bidder in cases where the successful bidder establishes a mistake, refuses to sign the contract, or fails to
furnish required bonds or insurance (see Public Contract Code Sections 5100-5107).
FISCAL IMPACT:
This project is funded by 90% Federal Aviation Administration (FAA) Airport Improvement Program (AIP) Funds,
2.25% Caltrans Funds, 7.75% Airport Enterprise Funds.
BACKGROUND:
The above project was previously approved by the Board of Supervisors, plans and specifications were filed with the
Board, and bids were invited by the Public Works Director. On Tuesday, April 28, 2015, the Public Works
Department received bids from the following contractors:
BIDDER TOTAL AMOUNT, BOND AMOUNTS
Maxwell Asphalt, Inc.: $851,353.48; Payment Bond: $851,353.48; Performance Bond: $851,353.48
Alaniz Construction, Inc.: $863,298.01
The bidder listed first above, Maxwell Asphalt, submitted the lowest responsive and responsible bid, which is
$11,944.53 less than the next lowest bid.
Per the requirements of the FAA and Section 3.1.04, Contract Award of the special provisions, the lowest responsible
bidder’s proposal is required to be submitted to FAA for approval and allocation of funds. Once FAA approves
funding, the Public Works Director can execute the contract with Maxwell Asphalt. If FAA does not approve the
funds the contract will not be awarded.
This is a federally-funded project subject to a DBE contract goal and requirements. The Public Works Director has
determined and reports that Maxwell Asphalt attained 20.93% DBE participation, which exceeds the DBE goal for
this project and the Public Works Director recommends that the construction contract be awarded to Maxwell
Asphalt.
The Public Works Director recommends that the bid submitted by Maxwell Asphalt, is the lowest responsive and
responsible bid, and this Board so concurs and so finds.
The Board of Supervisors previously determined that the project is exempt from the California Environmental Quality
Act as a Class II Exemption, and a Notice of Exemption was filed with the County Clerk on April 4, 2012.
The general prevailing rates of wages, which shall be the minimum rates paid on this project, have been filed with
the Clerk of the Board, and copies will be made available to any party upon request.
CONSEQUENCE OF NEGATIVE ACTION:
Construction of the Byron Airport Pavement Enhancements Project would be delayed, and the project might not be
built.