HomeMy WebLinkAboutMINUTES - 07212015 - C.87RECOMMENDATION(S):
Approve and authorize the Health Services Director, or his designee, to execute, on behalf of the County, Contract
Amendment Agreement #26-692-8 with Applied Remedial Services, Inc., a corporation, effective June 1, 2015, to
increase the payment limit by $3,500, from $290,000 to a new payment limit of $293,500, with no change in the
original term of January 1, 2015 through December 31, 2015.
FISCAL IMPACT:
This amendment is funded 100% in the Hospital Enterprise I Fund. (No rate increase)
BACKGROUND:
On January 6, 2015, the Board of Supervisors approved Contract #26-692-6 with Applied Remedial Services, Inc.,
for the period from January 1, 2015 through December 31, 2015, for the provision of removal and disposal of
hazardous waste and chemicals for the Contra Costa Regional Medical Center and Contra Costa Health Centers.
Approval of Contract Amendment Agreement #26-692-8 will allow the Contractor to provide additional removal and
disposal of hazardous waste including an additional pick up at the
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 07/21/2015 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Candace Andersen, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
ABSENT:Federal D. Glover, District V
Supervisor
Contact: Anna Roth, 370-5101
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: July 21, 2015
David Twa, County Administrator and Clerk of the Board of Supervisors
By: Chris Heck, Deputy
cc: T Scott, N Rios
C. 87
To:Board of Supervisors
From:William Walker, M.D., Health Services Director
Date:July 21, 2015
Contra
Costa
County
Subject:Amendment #26-692-8 with Applied Remedial Services, Inc.
BACKGROUND: (CONT'D)
Detention Facility in Martinez, through December 31, 2015.
CONSEQUENCE OF NEGATIVE ACTION:
If this amendment is not approved, the Contractor will not be able to provide hazardous waste removal and disposal
for the Detention Facility in Martinez.
CHILDREN'S IMPACT STATEMENT:
Not applicable.