APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a temporary permit for ingress and
egress purposes with Chevron U.S.A., Inc., effective March 31, 2015 through December 31, 2015, for the North
Richmond Pump Station Storm Water Diversion Project. (Project No.: 7517-6W7246)
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
The County is preparing for construction of the North Richmond Pump Station Storm Water Diversion Project
(Project).
In order to move forward with Project construction, the County needs a temporary permit for ingress and egress
(Permit) to occupy a 30-foot-wide portion of Assessor's Parcel Number 561-110-040 (Property). The Property the
County needs to occupy and use is owned by Chevron U.S.A., Inc. (Property Owner) and is adjacent to and west of
the County's pump station property.
The Permit will allow the County to occupy the Property for Project construction until the Project is completed, or
December 31, 2015, whichever occurs first. As a condition of the Permit, the Property Owner has required the
County to indemnify the Property Owner for claims arising out of the County's use of the Property or the construction
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 06/09/2015 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Candace Andersen, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
ABSENT:Federal D. Glover, District V
Supervisor
Contact: Angela Bell, 925-313-2337
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: June 9, 2015
David Twa, County Administrator and Clerk of the Board of Supervisors
By: June McHuen, Deputy
cc:
C.180
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:June 9, 2015
Contra
Costa
County
Subject:Temporary Permit for Ingress & Egress for North Richmond Pump Station Storm Water Diversion Project
BACKGROUND: (CONT'D)
of the Project.
Because the County needs access to the Property to construct the Project, County staff recommends that the Board
of Supervisors authorize the execution of the Permit.
CONSEQUENCE OF NEGATIVE ACTION:
The construction phase will not be able to move forward.