HomeMy WebLinkAboutMINUTES - 04142015 - C.51RECOMMENDATION(S):
(1) APPROVE the design, plans, and specifications for the above project.
(2) DETERMINE that the bid submitted by Valentine Corporation (“Valentine”) complied with the requirements of
the County’s Outreach Program for this project, as provided in the project specifications, and FURTHER
DETERMINE that Valentine submitted the lowest responsive and responsible bid for this project.
(3) AWARD the construction contract for the above project to Valentine in the amount of $469,369 and DIRECT that
the Public Works Director, or designee, prepare the contract.
(4) DIRECT that Valentine shall submit two good and sufficient security bonds (performance and payment bonds) in
the amount of $469,369 each.
(5) ORDER that, after the contractor has signed the contract and returned it, together with the bonds, evidence of
insurance, and other required documents, and the Public Works Director has reviewed and found them to be
sufficient, the Public Works Director, or designee, is authorized to sign the contract for this Board.
(6) ORDER that, in accordance with the project specifications and/or upon signature of the contract by the Public
Works Director, or designee, any bid bonds posted by the bidders are to be exonerated and any checks or cash
submitted for security shall be returned.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 04/14/2015 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Candace Andersen, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
ABSENT:Federal D. Glover, District V
Supervisor
Contact: Ramesh Kanzaria, (925)
313-2000
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of
Supervisors on the date shown.
ATTESTED: April 14, 2015
David Twa, County Administrator and Clerk of the Board of Supervisors
By: Chris Heck, Deputy
cc: PW Accounting, PW CPM Division Manager, PW CPM Clerical, Auditor's Office, County Counsel's Office, County Administrator's Office, County Administrator's Office
C. 51
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:April 14, 2015
Contra
Costa
County
Subject:AWARD Construction Contract for the North Richmond Pump Station Diversion Project (WJ7246)
RECOMMENDATION(S): (CONT'D)
(7) AUTHORIZE the Public Works Director, or designee, to sign any escrow agreements prepared for this project to
permit the direct payment of retentions into escrow or the substitution of securities for moneys withheld by the
County to ensure performance under the contract, pursuant to Public Contract Code Section 22300.
(8) AUTHORIZE the Public Works Director, or designee, to order changes or additions to the work pursuant to
Public Contract Code Section 20142.
(9) DELEGATE, pursuant to Public Contract Code Section 4114, to the Public Works Director, or designee, the
Board’s functions under Public Contract Code Sections 4107 and 4110.
(10) DECLARE that, should the award of the contract to Valentine be invalidated for any reason, the Board would
not in any event have awarded the contract to any other bidder, but instead would have exercised its discretion to
reject all of the bids received. Nothing in this Board Order shall prevent the Board from re-awarding the contract to
another bidder in cases where the successful bidder establishes a mistake, refuses to sign the contract, or fails to
furnish required bonds or insurance (see Public Contract Code Sections 5100-5107).
FISCAL IMPACT:
Funding for this project is provided by 63% Environmental Protection Agency grant funds and 37% Stormwater
Utility Area 17 Assessments.
BACKGROUND:
The purpose of the project is to participate in a pilot project to divert storm water to a sanitary district treatment plant
to determine the feasibility of treating storm water at a wastewater treatment plant before it is discharged into a
receiving water body. The project will divert storm water from the existing North Richmond Pump Station to a West
County Wastewater District sewer main on Gertrude Avenue. The diversion will be conducted on a temporary basis.
Inside the existing pump station, two new pumps will be installed (currently estimated at 250 gallons/minute
capacity) into the wet well of the existing pump station, automated level sensors will be installed to operate the new
pumps, and a new circuit breaker and control panel will be installed. Installation of the new pumps will also help
rehabilitate the pump station which is in need of repair.
Plans and specifications for the project have been prepared for the Public Works Department by LCA Architects and
filed with the Clerk of the Board by the Public Works Director. Bids were received and opened by the Public Works
Department on March 10, 2015, and the bid results are as follows:
BIDDER BASE BID
Valentine Corporation, San Rafael $469,369
Fort Bragg Electric, Fort Bragg $474,850
Bamer Construction Co., Castro Valley $539,000
All three bids received were above the Architect's Estimate of $345,000. Staff has evaluated the low bid submitted by
Valentine and their good faith effort documentation. Staff has determined that Valentine's bid is responsive and their
good faith effort documentation is in compliance with the County's Outreach Program. The Public Works Director
recommends the Board award the construction contract for this project to Valentine, the lowest responsible and
responsive bidder, in the amount of $469,369.
The general prevailing rates of wages, which shall be the minimum rates paid on this project, are on file with the
Clerk of the Board, and copies are available to any party upon request.
CONSEQUENCE OF NEGATIVE ACTION:
If the project is not approved, the County and Cities in the County will not meet the requirements of their stormwater
If the project is not approved, the County and Cities in the County will not meet the requirements of their stormwater
permit issued by the Regional Water Quality Control Board. In addition, the existing pump station will continue to
deteriorate and will ultimately be unable to protect the community from flooding.
CHILDREN'S IMPACT STATEMENT:
Not applicable.