HomeMy WebLinkAboutMINUTES - 04142015 - C.02RECOMMENDATION(S):
APPROVE and AUTHORIZE the Chair, Board of Supervisors, to execute Amendment No. 2 to Agreement No. 362
with the Contra Costa Transportation Authority (CCTA), to increase the amount payable to Contra Costa County by
$80,000 to a new payment limit of $755,000, to provide right of way services to CCTA for the I-80/San Pablo Dam
Road Interchange Improvement Project, San Pablo area. Project No. 4660-6X4170
FISCAL IMPACT:
Contra Costa Transportation Authority will pay the actual costs of right of way services performed by the Real
Estate Division, up to the payment limit as amended.
BACKGROUND:
CCTA requires a variety of right of way services related to the I-80/San Pablo Dam Road Interchange Improvement
project, but has no right of way staff and has contracted with the County for these services. On December 4, 2012, the
Board approved the original agreement between the County and CCTA. The parties wish to modify the scope of
services to include additional right of way services for an ongoing condemnation, coordinating clean-up of
contaminated soils, property management and additional maintenance clean-up, and file close-out activities.
CONSEQUENCE OF NEGATIVE ACTION:
CCTA will not be able to contract for the County’s right of way services and will not meet the terms of the
agreement.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 04/14/2015 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Candace Andersen, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
ABSENT:Federal D. Glover, District V
Supervisor
Contact: Karen Laws (925) 313-2228
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: April 14, 2015
David Twa, County Administrator and Clerk of the Board of Supervisors
By: Stacey M. Boyd, Deputy
cc:
C. 2
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:April 14, 2015
Contra
Costa
County
Subject:Contra Costa Transportation Authority Agreement No. 362 Amendment No. 2, I-80/San Pablo Dam Road Interchange
Improvement Project.
CHILDREN'S IMPACT STATEMENT:
Not applicable.
ATTACHMENTS
Staff Report
Amendment No. 2