HomeMy WebLinkAboutMINUTES - 02102015 - C.06RECOMMENDATION(S):
ACCEPT the attached report from the Contra Costa County Flood Control and Water Conservation District (Flood
Control District) on the 2014 Status of Flood Protection Infrastructure and;
DIRECT the Chief Engineer, Flood Control District, or designee, to implement the Action Plans in the report, with a
follow-up report to this Board annually and;
REFER the Flood Control District’s efforts to develop sustainable funding for flood protection to the Transportation,
Water and Infrastructure Committee (TWIC).
FISCAL IMPACT:
Preparation of this report cost $25,000, which was funded by Flood Control District Funds. Implementation of the
recommended action plans and assessment studies over the next fourteen years will cost approximately $9,000,000 to
be funded by Flood Control District and Flood Control Zone Funds, with efforts to offset expenses with grant funds.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 02/10/2015 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
ABSENT:Candace Andersen, District II
Supervisor
Contact: Tim Jensen (925) 313-2390
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: February 10, 2015
David Twa, County Administrator and Clerk of the Board of Supervisors
By: Stacey M. Boyd, Deputy
cc: D. Twa, County Administrator, T. Geiger, County Counsel's Office, S. Hymes-Offord, Risk Management, B. Burkhart, CCTV, S. Kowalewski, Deputy
Chief Engineer, M. Carlson, Flood Control, T. Jensen, Flood Control, C. Windham, Flood Control
C. 6
To:Contra Costa County Flood Control District Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:February 10, 2015
Contra
Costa
County
Subject:Report on 2014 Status of Flood Protection Infrastructure, Countywide. (100% Flood Control District Funds) Project
No. 7505-6F8135
BACKGROUND:
On November 5, 2013, the Flood Control District presented to the Board its first annual report on flood protection
infrastructure in order to understand its history, condition, and future needs. The attached report entitled “2014
Status of Flood Protection Infrastructure” provides information regarding the Flood Control District’s
accomplishments since the 2013 Annual Report and recommends pursuing sustainable funding for flood
protection.
In summary, our community outreach events were successful, our capital programs made progress, and our studies
of aging infrastructure and unsustainable service levels continued to highlight some major concerns, primarily
regarding sustainability.
A more detailed look at the Flood Control District’s financial picture was performed this past year. Maintenance
funding for regional Flood Control District facilities comes primarily from a percentage of the 1% ad valorem
property tax. Maintenance funding for community drainage facilities comes from annual assessments from each
stormwater utility area, formed in 1993. Prior to that time, the County’s community drainage maintenance was
paid for out of County General Funds. Road system drainage maintenance is funded by a portion of the local
share of gas tax. Each city funds their own community drainage systems, typically with their stormwater utility
fees.
We found that the Flood Control District regional flood protection facilities and unincorporated community
drainage facilities funding is inadequate. Historical expenditures have been capped due to limited revenue,
resulting in service levels being at the bare minimum. After several years of this practice, the outcome has been
poor facility conditions and an increasing backlog of deferred maintenance. The current funding level for our
regional and community drainage maintenance is about $5 million per year, which is about 0.4% of our
infrastructure value. To meet the industry standard for sustainable maintenance of 2% of infrastructure value, the
funding need is about $24 million per year.
When regional planning, capital improvement, and capital replacement needs are added to the maintenance need,
the annual funding shortfall is approximately $78 million, as compared to the current revenue of about $8.9
million. We are now including capital replacement needs in our financial planning, because in 2029, the first
regional flood protection facility reaches its expected service life of 75 years and will need replacement or major
rehabilitation soon thereafter.
Historically, Flood Control District regional flood protection has not needed County General Fund support.
Inadequate funding has been managed by reduced service delivery, deferred maintenance, deferred capital
improvements, and loans from the Flood Control District. This is not sustainable as the Flood Control District fund
is projected to be depleted in less than 10 years. Once that occurs, there is no backstop source of revenue other
than County General Funds. Due to increases in community drainage maintenance costs, the need for County
General Funds (provided prior to 1993) has returned.
Most flood protection, drainage, and stormwater agencies statewide suffer from inadequate funding. Proposition
13 froze tax rates at low levels, and Proposition 218 made it difficult to increase revenue. The County has been
working with the California State Association of Counties and the County Engineers Association of California on
a Statewide Stormwater Funding Initiative to exempt stormwater agencies from Proposition 218 voter
requirements, similar to the exemption that water and wastewater utility districts have. Support is building across
the state, and legislation will be introduced in early 2015 to initiate this funding measure. We recommend that the
County continue to support the legislative effort to get this funding measure into place.
The Flood Control District will continue implementation of the action plans outlined in the 2013 Annual Report.
The key action for the next few years will be to focus on developing sustainable funding for regional flood
protection and community drainage.
Staff recommends that the Board accept the attached 2014 Status of Flood Protection Infrastructure Report from
the Flood Control District, direct the Chief Engineer to continue with the Action Plans recommended in the
Report, with a follow-up report to this Board annually, as well as refer the effort to develop sustainable funding
for regional flood protection and community drainage to the TWIC.
CONSEQUENCE OF NEGATIVE ACTION:
The County’s flood protection and community drainage infrastructure funding issues will not be adequately
addressed, which will lead to lower levels of flood protection for our communities in the future.
CHILDREN'S IMPACT STATEMENT:
Not directly applicable.
ATTACHMENTS
2014 Status Report
2014 Annual Report
CONTRA COSTA COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT
2014 Status of Flood Protection Infrastructure | 1/27/2015 2
We have accomplished much in 2014, including community celebrations, native plantings, trash cleanups,
creating a safety video, improving swiftwater rescue, receiving a quarter million dollars in grant funding for
flood safety improvements, completing a $14 million dollar flood protection basin, starting our pilot
infrastructure assessment program, and evaluating our financial condition. Our diverse community outreach
events engaged hundreds of people from across the County, helping to increase local support for the Flood
Control District.
Financial reporting reinforced our concerns that our aging infrastructure and unsustainable service levels are
headed for a crisis. Almost 40% of our $1 billion of flood protection infrastructure will be over 50 years old by
by 2020. Our current funding only allows for maintenance service levels at 22% of what it should be per
industry standard. To continue providing County-wide flood protection into the future, we need additional
funds for maintenance, capital programs, and facility replacement. Our primary focus will be on additional
funding until we have achieved financial sustainability.
Once again, 2014 found the Flood Control District in the community, and working not only for our residents,
but with them. By partnering even more this year, we will increase community engagement to help build a
sustainable future.
Since the District’s last report in November 2013 we have accomplished the following:
The District implemented the Giving the Natives a Chance program, which focused on engaging the
community in the District’s facilities. In December 2013, we partnered with the non-profit Restoration Trust
and held our first planting in the Clayton Valley Drain. The event was well attended, and 90 volunteers
planted 1,600 native grasses and sedges as part of an experiment to study ways to reduce invasive grasses
and herbicide use in flood control channels. A follow-up event was held in December 2014. Thirty volunteers
returned to plant 1,800 plugs to bolster the native grasses and sedges.
The next volunteer event was held when the District celebrated the completion of the Upper Sand Creek
Basin project. A planting day was held in partnership with the Friends of Marsh Creek Watershed. In just a
few hours, 150 volunteers planted 400 native plants from the Flood Control District’s volunteer nursery in the
10-acre restored wetland area. This project was unique in that the native plant seeds were harvested from the
site prior to construction, grown and cared for by District staff, and then returned to the site.
After years of legislative effort, Lower Walnut Creek was returned to local control when President Obama
signed Water Resources Development Act 2014 in June. This removed the lowest four miles of Walnut and
Pacheco Creeks from the Army Corps of Engineers control. This allows the District to move forward with a
community-based restoration planning effort that incorporates flood protection, wetland restoration, and
recreation opportunities. To celebrate, a media event was held in July at the Pacheco Marsh. Speakers
included Congressman Mike Thompson, and representatives from the Board of
Supervisors, East Bay Regional Park District, and Muir Heritage Land Trust.
A report was issued by the Army Corps of Engineers listing levee deficiencies in the
stretch of Walnut Creek that remained under federal jurisdiction, which resulted in
several unacceptable ratings and delisting from disaster relief funding. Our
investigation found that the ratings were due to inaccurate data by the Corps, as well
as reduced levels of maintenance from the District. Those issues will be resolved in
2015 allowing the Corps of Engineers to reinstate our disaster relief funding.
Message from Julie Bueren, Chief Engineer
1.0 Summary of Accomplishments
3 2014 Status of Flood Protection Infrastructure | 1/27/2015
Thanks to the assistance of the County’s Public Information Officer and CCTV the District continued
developing our Communication and Outreach plan. This included planning and
producing targeted media releases and creating an outreach video.
The Creek and Channel Safety Awareness Program
remained a priority. We created a kid-friendly safety video
with the students of Mt. Diablo High School’s Digital Safari
Academy in the spring. In the summer we worked with the
Contra Costa County Fire Protection District Swiftwater
Rescue Team to install improvements at their primary
rescue site for the Walnut Creek channel, and provided
funding for swiftwater rescue equipment for training and
use in County waterways.
The consultant selection process was completed for the Conditions Assessment of
Critical Infrastructure program, and we made significant progress on our pilot program
to assess facilities in three watersheds.
Progress was made on our capital projects. Upper Sand Creek Basin was completed
in April. This $14 million project was the largest locally-funded project in District history. Design of the
Wildcat and San Pablo Creeks Critical Levee Repair Project is nearing completion. This project would not
have been possible without a $1.5 million grant obtained in 2013, or the State’s 90% contribution, requiring
only a 10% match. It will protect the community of North Richmond from flooding impacts, and meets strict
Army Corps of Engineers and FEMA standards.
We received a $250,000 grant from the State to install ten stream gages in critical areas which will provide
better data for flood prediction and warning, improving community flood safety.
In 2014 two new performance measures were adopted regarding; 1) the level of flood protection provided to
communities, and 2) Flood Control District undesignated fund balance.
2.1 Level of Flood Protection: A composite view of
the level of flood protection provided by all regional
flood protection facilities showed that, on average,
they provide 90% of the target level of flood
protection. When these facilities were new, they
provided 100% of their designed level of flood
protection. Due to factors such as increased
urbanization, higher flood protection standards, as
well as decreased maintenance service and funding,
the level of flood protection provided by our regional
facilities has been in decline. The FC District will
continue to evaluate this benchmark every five years
and develop action plans to address the various
factors involved, with the goal to return to 100%
level of flood protection provided for all facilities.
2.0 Performance Measures
Level of Flood Protection Performance Measure
4 2014 Status of Flood Protection Infrastructure | 1/27/2015 2.2 Flood Control District Undesignated Fund
Balance: Funding for maintenance of regional
flood protection facilities comes primarily from a
percentage of the 1% ad valorem tax. Revenues
have been capped as a result of Proposition 13
and 218, thus staff has had to redistribute revenue
to fund basic maintenance for drainage area
zones that have zero revenue or inadequate
revenue. The redistribution of funds is achieved
through the District’s revolving fund loan program,
typically borrowing funds from the District’s
undesignated fund. Over the years, the loan
balance has grown to $4.5 million, and the
remaining undesignated fund balance has
decreased to $3.4 million. A target undesignated
fund balance was set for 2014 at $7.7 million to keep a buffer for annual operating expenses above the loan
balance, so the $3.4 million fund balance is currently only 44% of the target level.
Continuing these loans, even when coupled with lower service levels, deferred maintenance, and deferred
capital improvement, is not sustainable, and the undesignated fund is projected to be depleted in less than 10
years. Once that occurs, there is no backstop source of revenue, and County General Funds may be
needed.
The Flood Control District was formed in 1951 to provide regional flood protection for Contra Costa County.
Since then, 79 miles of channels and 29 detention basins have been constructed. The estimated asset value
is over $1 billion (in 2010 dollars), and the facilities protect an estimated $25 billion in property value in
historic floodplains. Federal and State government programs funded 90 to 95 percent of the construction
costs. These regional facilities collect stormwater from community drainage systems in the developed
unincorporated County (and cities). Maintenance and capital funding for regional Flood Control District
facilities comes primarily from a percentage of the 1% ad valorem property tax. Maintenance funding for
community drainage facilities comes from stormwater utility assessments, which were established in 1993.
Prior to that time, community drainage maintenance was paid for out of County General Funds. Road system
drainage maintenance is funded by a portion of the local share of gas tax. Each city funds maintenance for
their community drainage systems, typically with their stormwater utility fees.
Maintenance funding was established when facilities were brand new and little expense was required, then
Proposition 13 froze those low rates. Since that time, expenditures have been capped due to limited revenue,
resulting in service levels being at the bare minimum. After many years of this practice, the outcome has
been poor facility conditions and an increasing backlog of deferred maintenance. The current funding level
for our regional and community drainage maintenance is about $5 million per year, which is about 0.4% of our
infrastructure value ($1.3 billion in 2010 dollars). To meet the industry standard for adequate maintenance
which is 2% of infrastructure value, the funding need is about $24 million per year. Our current funding level
is about 22% of the need. The initial level of maintenance funding which may have been adequate for brand
new facilities was not increased over time to the level necessary to adequately maintain aging facilities.
Since about 40% of our facilities will be 50 years or older in 2020, the lack of maintenance funding is
becoming more and more critical.
Performance Measure: Undesignated Fund Balance
3.0 Financial Summary
5 2014 Status of Flood Protection Infrastructure | 1/27/2015 When regional planning, capital improvement, and capital replacement needs are
added to the maintenance need, the annual funding need is approximately $83
million, compared to the current revenue of about $11.5 million. We are now
including capital replacement needs in our financial planning because in 2029 the
first regional flood protection facility reaches its expected service life of 75 years
and will need replacement or major rehabilitation soon thereafter. Overall, our
current revenue is 14% of the total estimated need. None of the regional flood
protection funding zones have adequate funding, and three have zero revenue.
For example, Wildcat Creek receives about $69,000 annually, which is 9% of the
$800,000 maintenance funding needed, and 1% of the $4.9 million total programs
funding need.
Historically, FC District regional flood protection has not needed County General
Fund support. Inadequate funding has been managed by reduced service
delivery, deferred maintenance, deferred capital improvements, and loans from
the FC District undesignated fund. This is not sustainable as the FC District undesignated fund is projected to
be depleted in less than 10 years. Once that occurs, there is no backstop source of revenue other than
County General Funds. Due to increases in community drainage maintenance costs, the need for County
General Funds (provided prior to 1993) has returned.
Figure 1 below graphically shows the funding history and projected annual need for sustainable funding levels
to adequately fund regional and community drainage programs. Please refer to our Financial Report on our
web page for more detail.
Most flood protection, drainage, and stormwater agencies statewide
suffer from inadequate funding. Proposition 13 froze tax rates at low
levels, and Proposition 218 has made it difficult to increase revenue.
Staff has already been working with statewide organizations such as
California State Association of Counties, County Engineers Association
of California, and others on a Statewide Stormwater Funding Initiative
to exempt stormwater agencies from Proposition 218 voter
Figure 1. Regional and Community Drainage Funding Need – All Programs
4.0 Potential Funding
$0
$20
$40
$60
$80
$100
$120
1980 1990 2000 2010 2020 2030
Funding Need
Revenue History
Projected Revenue
Millions Historical and Projected Funding: Annual Need
Fiscal Year End
6 2014 Status of Flood Protection Infrastructure | 1/27/2015 requirements, similar to how water and wastewater utility districts are funded. Support is building across the
state, and legislation will be introduced in early 2015 to initiate this funding measure. We recommend the
County continue its support of the legislative effort to get this funding measure into place.
We have made progress on some of the action plans presented in our November 2013 Annual Report (items
1 – 8 in Figure 2 below) and thus reduced the cost of future programs to approximately $9 million.
The Flood Control District’s aging infrastructure and unsustainable service levels are major concerns that
deserve attention, and in the near term we will focus primarily on seeking additional funding. Community
outreach events increased local support for the Flood Control District. Those events should be continued as
they are one of the key elements for building a sustainable future.
This effort to obtain sustainable funding sources is being
referred to the Transportation, Water, and Infrastructure
Committee for detailed study and recommendations.
For more information and previous Annual Reports, refer
to our web page at www.cccounty.us/FCDReports, or
contact Tim Jensen at tjens@pw.cccounty.us
# Action Plan Description Cost Estimate Time (years) Start
1 Sediment Studies at Channel Mouths $250,000 8 February 2008
2 Study Level of Flood Protection $1,640,000 14 December 2008
3 Review and Report on Financial Status $50,000 1 June 2012
4 Develop Financing Plan $50,000 1 June 2012
5 Develop Communication and Outreach Plan $100,000 1 February 2013
6 Improve Flood Forecasting and Warning Systems $300,000 2 April 2013
7 Conditions Assessment of Critical Infrastructure $5,500,000 7 - 9 October 2013
8 Seismic Study of 5 Dams $1,250,000 4 2015
Assessments Total: $9,140,000 14
Figure 2. Overall FC District Action Plans Cost and Schedule - 2014 Update
6.0 Conclusions and Recommendations
5.0 Action Plans Update