HomeMy WebLinkAboutMINUTES - 10072014 - C.15RECOMMENDATION(S):
APPROVE the Upper Sand Creek Basin project contingency fund increase of $1,000,000 for a new contingency fund
total of $2,911,688.50, and a new payment limit of $12,028,573.50, effective October 7, 2014, as recommended by
the Chief Engineer; and,
APPROVE and AUTHORIZE the Chief Engineer, or designee, to execute Contract Change Order No. 11 with
Goodfellow Top Grade Construction, LLC, effective October 7, 2014, for a total amount not to exceed $1,435,000 to
settle all claims on the above project, including Notices of Potential Claims Nos. 1-8 and disputed earthwork
quantities. (Project No. 7562-6D8518-10)
FISCAL IMPACT:
The increase in contingency funds will be funded by 100% Drainage Area 130 funds.
BACKGROUND:
The Project contingency funds are currently insufficient to cover the increased cost. The Contractor has filed eight
Notices of Potential Claim on the project related to project delays, weather delays, and changes in construction means
and methods to adapt to field constructability constraints, including constructing the dam embankment in stages and
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 10/07/2014 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Candace Andersen, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Kevin Emigh,
925-313-2320
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: October 7, 2014
David Twa, County Administrator and Clerk of the Board of Supervisors
By: Stacey M. Boyd, Deputy
cc: Julia Bueren, Public Works Director
C. 15
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:October 7, 2014
Contra
Costa
County
Subject:Contingency Fund Increase and Change Order #11 for the Upper Sand Creek Basin Project, Antioch area.
BACKGROUND: (CONT'D)
>
changing from trenching to open cut for the outlet works pipe installation. Earthwork quantities, and the need to
double-handle material due to changes in means and method, have also been disputed by the contractor. If
approved by the Board, this change order would constitute a global settlement of all potential claims and disputes
on the project. Otherwise, if not approved, the Contractor's claims would remain and the change order could not be
used against the District.
CONSEQUENCE OF NEGATIVE ACTION:
The lack of approval would preclude payment of the Contractor's claims on the above project and would delay
final project close-out.
CHILDREN'S IMPACT STATEMENT:
Not applicable.