HomeMy WebLinkAboutMINUTES - 10072014 - C.15RECOMMENDATION(S): APPROVE the Upper Sand Creek Basin project contingency fund increase of $1,000,000 for a new contingency fund total of $2,911,688.50, and a new payment limit of $12,028,573.50, effective October 7, 2014, as recommended by the Chief Engineer; and, APPROVE and AUTHORIZE the Chief Engineer, or designee, to execute Contract Change Order No. 11 with Goodfellow Top Grade Construction, LLC, effective October 7, 2014, for a total amount not to exceed $1,435,000 to settle all claims on the above project, including Notices of Potential Claims Nos. 1-8 and disputed earthwork quantities. (Project No. 7562-6D8518-10) FISCAL IMPACT: The increase in contingency funds will be funded by 100% Drainage Area 130 funds. BACKGROUND: The Project contingency funds are currently insufficient to cover the increased cost. The Contractor has filed eight Notices of Potential Claim on the project related to project delays, weather delays, and changes in construction means and methods to adapt to field constructability constraints, including constructing the dam embankment in stages and APPROVE OTHER RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE Action of Board On: 10/07/2014 APPROVED AS RECOMMENDED OTHER Clerks Notes: VOTE OF SUPERVISORS AYE:John Gioia, District I Supervisor Candace Andersen, District II Supervisor Mary N. Piepho, District III Supervisor Karen Mitchoff, District IV Supervisor Federal D. Glover, District V Supervisor Contact: Kevin Emigh, 925-313-2320 I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown. ATTESTED: October 7, 2014 David Twa, County Administrator and Clerk of the Board of Supervisors By: Stacey M. Boyd, Deputy cc: Julia Bueren, Public Works Director C. 15 To:Board of Supervisors From:Julia R. Bueren, Public Works Director/Chief Engineer Date:October 7, 2014 Contra Costa County Subject:Contingency Fund Increase and Change Order #11 for the Upper Sand Creek Basin Project, Antioch area. BACKGROUND: (CONT'D) > changing from trenching to open cut for the outlet works pipe installation. Earthwork quantities, and the need to double-handle material due to changes in means and method, have also been disputed by the contractor. If approved by the Board, this change order would constitute a global settlement of all potential claims and disputes on the project. Otherwise, if not approved, the Contractor's claims would remain and the change order could not be used against the District. CONSEQUENCE OF NEGATIVE ACTION: The lack of approval would preclude payment of the Contractor's claims on the above project and would delay final project close-out. CHILDREN'S IMPACT STATEMENT: Not applicable. ATTACHMENTS Change Order No. 11