HomeMy WebLinkAboutMINUTES - 10072014 - C.13RECOMMENDATION(S):
APPROVE and AUTHORIZE the Chief Engineer, or designee, to execute Amendment No. 4 of the Consulting
Services Agreement (CSA) with Consolidated CM (CCM), effective October 1, 2014, to increase the payment limit
by $200,000 to a new payment limit of $2,557,773, and extend the termination date from October 1, 2014 to June 1,
2015 in order to provide construction management services for the Upper Sand Creek Basin Project, Antioch area.
(Project No. 7562-6D8518-10)
FISCAL IMPACT:
CSA Amendment No. 4 allows for an increase in the payment limit. The increase is to be funded by 100% Drainage
Area 130 funds.
BACKGROUND:
The Upper Sand Creek Basin project is being constructed on Sand Creek to improve the flood protection to
downstream residents. Due to the large size of the project site, continued project delays, and eight notices of potential
claims being filed, the Consultant is providing additional staff time and sub-consultant services on the project.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 10/07/2014 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Candace Andersen, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Kevin Emigh,
925-313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: October 7, 2014
David Twa, County Administrator and Clerk of the Board of Supervisors
By: Stacey M. Boyd, Deputy
cc:
C. 13
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:October 7, 2014
Contra
Costa
County
Subject:Amendment No. 4 to Consulting Services Agreement with Consolidated CM, Antioch area.
BACKGROUND: (CONT'D)
On March 12, 2013, the Board of Supervisors approved the CSA for construction management services for the
construction of the project with Consolidated CM.
On December 3, 2013, the Board of Supervisors approved Amendment No. 1 increasing the payment limit for
additional construction management services.
On February 11, 2014, the Board of Supervisors approved Amendment No. 2 increasing the payment limit for
additional construction management services.
On May 13, 2014, the Board of Supervisors approved Amendment No. 3 increasing the payment limits for additional
construction management services for additional staff time due to continuing delays and four notices of potential
claims being filed.
Proposed Amendment No. 4 will amend payment limits and amend the contract termination date in order to provide
additional construction management services.
CONSEQUENCE OF NEGATIVE ACTION:
Public Works staff does not have the expertise to perform this work in-house. The consultant may not get