HomeMy WebLinkAboutMINUTES - 06242014 - C.08RECOMMENDATION(S):
(1) APPROVE plans, specifications, and design for the Stone Valley Road Bike Lane Gap Closure project, Project
No. 0662-6R4209.
(2) DETERMINE that Breneman, Inc. (“Breneman”), the lowest monetary bidder, has complied with the
requirements of the County’s Outreach Program for this project, as provided in the project specifications; and the
Board WAIVES any irregularities in such compliance; and FURTHER DETERMINE that Breneman has submitted
the lowest responsive and responsible bid for the project and has complied with the Mandatory Subcontracting
Minimum for the project.
(3) AWARD the construction contract for the above project to Breneman in the listed amount ($521,062.12) and the
unit prices submitted in the bid, and DIRECT that Breneman shall present two good and sufficient surety bonds, as
indicated below, and that the Public Works Director, or designee, shall prepare the contract.
(4) ORDER that, after the contractor has signed the contract and returned it, together with the bonds as noted below
and any required certificates of insurance or other required documents, and the Public Works Director has reviewed
and found them to be sufficient, the Public Works Director, or designee, is authorized to sign the contract for this
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD
COMMITTEE
Action of Board On: 06/24/2014 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYES 5 NOES ____
ABSENT ____ ABSTAIN ____
RECUSE ____
Contact: Kevin Emigh,
925-313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of
the Board of Supervisors on the date shown.
ATTESTED: June 24, 2014
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: Stacey M. Boyd, Deputy
cc:
C. 8
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:June 24, 2014
Contra
Costa
County
Subject:AWARD and AUTHORIZE execution of a construction contract for the Stone Valley Road Bike Lane Gap Closure
project, Alamo area.
RECOMMENDATION(S): (CONT'D)
Board.
(5) ORDER that, in accordance with the project specifications and/or upon signature of the contract by the Public
Works Director, or designee, bid bonds posted by the bidders are to be exonerated and any checks or cash submitted
for security shall be returned.
(6) ORDER that, the Public Works Director, or designee, is authorized to sign any escrow agreements prepared for
this project to permit the direct payment of retentions into escrow or the substitution of securities for moneys
withheld by the County to ensure performance under the contract, pursuant to Public Contract Code Section 22300.
(7) DELEGATE, pursuant to Public Contract Code Section 4114, to the Public Works Director, or designee, the
Board’s functions under Public Contract Code Sections 4107 and 4110.
(8) DELEGATE, pursuant to Labor Code Section 6705, to the Public Works Director, or to any registered civil or
structural engineer employed by the County, the authority to accept detailed plans showing the design of shoring,
bracing, sloping, or other provisions to be made for worker protection during trench excavation covered by that
section.
(9) DECLARE that, should the award of the contract to Breneman be invalidated for any reason, the Board would not
in any event have awarded the contract to any other bidder, but instead would have exercised its discretion to reject
all of the bids received. Nothing in this Board Order shall prevent the Board from re-awarding the contract to another
bidder in cases where the successful bidder establishes a mistake, refuses to sign the contract, or fails to furnish
required bonds or insurance (see Public Contract Code Sections 5100-5107).
FISCAL IMPACT:
The construction contract will be funded by 62% Measure J- Transportation for Livable Communities (LTC) Grant
Funds and 38% Alamo Area of Benefit (AOB) Funds.
BACKGROUND:
The above project was previously approved by the Board of Supervisors, plans and specifications were filed with the
Board, and bids were invited by the Public Works Director. On May 27, 2014, the Public Works Department received
bids from the following contractors:
BIDDER, TOTAL AMOUNT, BOND AMOUNTS
Breneman: $521,062.12; Payment: $521,062.12; Performance: $521,062.12
Sposeto Engineering, Inc.: $810,690.50
The Public Works Director has reported that Breneman documented an adequate good faith effort to comply with the
requirements of the County’s Outreach Program, as provided in the project specifications, and the Public Works
Director recommends that the construction contract be awarded to Breneman.
The Public Works Director recommends that the bid submitted by Breneman is the lowest responsive and responsible
bid, and this Board concurs and so finds.
The Board of Supervisors previously determined that the project is exempt from the California Environmental Quality
Act as a Class 2 Exemption, and a Notice of Exemption was filed with the County Clerk on February 27, 2014.
The general prevailing rates of wages, which shall be the minimum rates paid on this project, have been filed with
the Clerk of the Board, and copies will be made available to any party upon request.
CONSEQUENCE OF NEGATIVE ACTION:
Construction of the project would be delayed, and the project might not be built.
CHILDREN'S IMPACT STATEMENT:
Not applicable.