HomeMy WebLinkAboutMINUTES - 06242014 - C.06RECOMMENDATION(S):
APPROVE and AUTHORIZE the Public Works Director, or designee, to execute the Temporary Surveys Permit with
HJSCMB-Donovan, LLC, a California limited liability company (Property Owners), effective June 24, 2014 through
December 31, 2019, for the Kirker Pass Road Northbound Truck Lanes Project. Project No.: 0662-6R4052
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
The Contra Costa County (County) Public Works Department is required to conduct geotechnical surveys prior to
design and during construction of the Kirker Pass Road Northbound Truck Lanes Project. It is necessary to conduct
these surveys to identify the stability measurements of the property after the initial drilling operation is completed
through the estimated end of construction. As a condition of the permit, the Property Owners have required the
County to indemnify the Property Owners.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD
COMMITTEE
Action of Board On: 06/24/2014 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYES 5 NOES ____
ABSENT ____ ABSTAIN ____
RECUSE ____
Contact: Jann Edmunds,
925-313-2250
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of
the Board of Supervisors on the date shown.
ATTESTED: June 24, 2014
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: Stacey M. Boyd, Deputy
cc: Nancy Wein, PW, TE
C. 6
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:June 24, 2014
Contra
Costa
County
Subject:Temporary Surveys Permit for Kirker Pass Road Northbound Truck Lanes Project.
CONSEQUENCE OF NEGATIVE ACTION:
The construction phase will not be able to move forward.
CHILDREN'S IMPACT STATEMENT:
Not applicable.
ATTACHMENTS
Temporary Surveys Permit