HomeMy WebLinkAboutMINUTES - 06172014 - C.02RECOMMENDATION(S):
(1) APPROVE plans, specifications, and design for the Deer Valley Road Shoulder Widening project. Project No.
0662-6R4099-14, Federal Project No. HRRRL-5928(084)
(2) DETERMINE that the bid submitted by Bay Cities Paving & Grading, Inc. (“Bay Cities”), exceeded the DBE
(Disadvantaged Business Enterprise) goal for this project and that Bay Cities has submitted the lowest responsive and
responsible bid for this project.
(3) AWARD the construction contract for the above project to Bay Cities, in the listed amount ($687,054.89) and the
unit prices submitted in the bid and DIRECT that Bay Cities shall present two good and sufficient surety bonds as
indicated below, and that the Public Works Director, or designee, shall prepare the contract.
(4) ORDER that, after the contractor has signed the contract and returned it, together with the bonds as noted below
and any required certificates of insurance or other required documents, and the Public Works Director has reviewed
and found them to be sufficient, the Public Works Director, or designee, is authorized to sign the contract for this
Board.
(5) ORDER that, in accordance with the project specifications and/or upon signature of the contract by the Public
Works Director, or designee, any bid bonds posted by the bidders are to be exonerated and any checks or cash
submitted for security shall be returned.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 06/17/2014 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Candace Andersen, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Kevin Emigh,
925-313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: June 17, 2014
David Twa, County Administrator and Clerk of the Board of Supervisors
By: Stacey M. Boyd, Deputy
cc:
C. 2
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:June 17, 2014
Contra
Costa
County
Subject:Execute a construction contract for the Deer Valley Road Shoulder Widening Project, Brentwood area.
RECOMMENDATION(S): (CONT'D)
(6) ORDER that, the Public Works Director, or designee, is authorized to sign any escrow agreements prepared for
this project to permit the direct payment of retentions into escrow or the substitution of securities for moneys
withheld by the County to ensure performance under the contract, pursuant to Public Contract Code Section 22300.
(7) DELEGATE, pursuant to Public Contract Code Section 4114, to the Public Works Director, or designee, the
Boards’ functions under Public Contract Code Sections 4107 and 4110.
(8) DELEGATE, pursuant to Labor Code Section 6705, to the Public Works Director, or to any registered civil or
structural engineer employed by the County, the authority to accept detailed plans showing the design of shoring,
bracing, sloping, or other provisions to be made for worker protection during trench excavation covered by that
section.
(9) DECLARE that, should the award of the contract to Bay Cities be invalidated for any reason, the Board would not
in any event have awarded the contract to any other bidder, but instead would have exercised its discretion to reject
all of the bids received. Nothing in this Board Order shall prevent the Board from re-awarding the contract to another
bidder in cases where the successful bidder establishes a mistake, refuses to sign the contract, or fails to furnish
required bonds or insurance (see Public Contract Code Sections 5100-5107).
FISCAL IMPACT:
The construction contract will be funded by 38% Federal High Risk Rural Road Program Funds, 44% Proposition 1 B
Funds, 18% Local Road Funds.
BACKGROUND:
The above project was previously approved by the Board of Supervisors, plans and specifications were filed with the
Board, payment to the Habitat Conservancy Plan for $41,771.15 will be paid by June 17, 2014, and bids were invited
by the Public Works Director. On May 20, 2014, the Public Works Department received bids from the following
contractors:
BIDDER TOTAL AMOUNT, BOND AMOUNTS
Bay Cities Paving & Grading, Inc.: $687,054.89; Payment: $687,054.89; Performance: $687,054.89
Grade Tech, Inc.: $752,691.50
Granite Rock Company: $774,199.00
Robert Burns Construction, Inc.: $ 802,371.85
Hess Construction Co., Inc.: $821,877.00
TCB Industrial, Inc.: $852,679.71
The bidder listed first above, Bay Cities, submitted the lowest responsive and responsible bid, which is $65,636.61
less than the next lowest bid.
The Public Works Director has determined and reports that Bay Cities attained 21.39% DBE participation, which
exceeds the DBE goal for this project and the Public Works Director recommends that the construction contract be
awarded to Bay Cities .
The Public Works Director recommends that the bid submitted by Bay Cities, is the lowest responsive and
responsible bid, and this Board so concurs and so finds.
The Board of Supervisors previously adopted the Mitigated Negative Declaration and Mitigation and Monitoring
Reporting Plan in compliance with the California Environmental Quality Act, and a Notice of Determination was
filed with the County Clerk on July 13, 2011.
The general prevailing rates of wages, which shall be the minimum rates paid on this project, have been filed with
the Clerk of the Board, and copies will be made available to any party upon request.
CONSEQUENCE OF NEGATIVE ACTION:
Construction of the Deer Valley Road Shoulder Widening project would be delayed, and the project might not be
built.
CHILDREN'S IMPACT STATEMENT:
Not applicable.