HomeMy WebLinkAboutMINUTES - 01142014 - C.10RECOMMENDATION(S):
ADOPT Position Adjustment Resolution No. 21401 to add one (1) full time Manager, Application and Permit Center
(5PDB) (represented) at salary level ZA2 1622 ($5,334 - $7,537) and one (1) full time Principal Structural Engineer
(NCHA) (represented) at salary level ZA5 1962 ($7,249- $8,812) in the Department of Conservation and
Development.
FISCAL IMPACT:
No impact to County General Fund. The annual cost for these additional positions is approximately $306,000 of
which approximately $74,000 represent retirement costs. Savings of approximately $195,000 accrued by freezing a
vacant Engineering Manager position will assist in offsetting the costs of these positions. The positions are 100%
funded by Land Development revenues.
BACKGROUND:
Following the departure of the Supervising Engineer, the department is reallocating the duties in order to improve
efficiency for the public and to respond to an increase in land development activities. The Principal Engineer will
oversee engineering services for the department (with the exception of the Lamorinda area). The Permit Center
Manager will be responsible for the Building Plan Checking Team, the Planning Counter Services Team and a new
initiative that will focus on accelerating the review and approval of small land development permits.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 01/14/2014 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Candace Andersen, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Victoria Mejia (925)
674-7726
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: January 14, 2014
David Twa, County Administrator and Clerk of the Board of Supervisors
By: June McHuen, Deputy
cc: Roxana Mendoza, Victoria Mejia
C. 10
To:Board of Supervisors
From:Catherine Kutsuris, Conservation and Development Director
Date:January 14, 2014
Contra
Costa
County
Subject:Add one (1) full time Manager, Application Permit Center (5PDB) and add one (1) full time Principal Structural
Engineer (NCHA)
CONSEQUENCE OF NEGATIVE ACTION:
Failure to receive Board Approval will impede the department’s ability to efficiently perform engineering and
plan check services as well as to implement new efficiencies.
CHILDREN'S IMPACT STATEMENT:
None.
ATTACHMENTS
P300 21401 APC Mgr and Princ Struct Eng at DCD