HomeMy WebLinkAboutMINUTES - 12102013 - C.01RECOMMENDATION(S):
APPROVE the Marsh Creek Wingwall Repair Project and AUTHORIZE the Public Works Director, or designee, to
advertise the project [DCD-CP#13-12], Project No.: 0662-6U4091
DETERMINE the project is a California Environmental Quality Act (CEQA), Class 1(b) Categorical Exemption,
pursuant to Section 15301(b) of the CEQA Guidelines, and
DIRECT the Director of Conservation and Development to file a Notice of Exemption with the County Clerk, and
AUTHORIZE the Public Works Director to arrange for payment of a $25 fee to Conservation and Development for
processing, and a $50 fee to the County Clerk for filing the Notice of Exemption.
FISCAL IMPACT:
100% Local Road Funds.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 12/10/2013 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Candace Andersen, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: L. Chavez,
925-313-2366
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: December 10, 2013
David Twa, County Administrator and Clerk of the Board of Supervisors
By: Stacey M. Boyd, Deputy
cc:
C. 1
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:December 10, 2013
Contra
Costa
County
Subject:APPROVE the Marsh Creek Wingwall Repair Project and CONSIDER related actions under California
Environmental Quality Act, Clayton area.
BACKGROUND:
The purpose of the work is to repair two of the wingwalls on Marsh Creek Road Bridge 142 that retain fill under
the road. The wingwall on the southeast side of the bridge has failed and fallen into the creek. The failed wingwall
is a reinforced concrete wall that will be removed and replaced with a new wingwall. The wingwall on the
northwest side of the bridge is leaning and will be repaired by securing it to the existing slope behind the
wingwall with tie backs (long nails) into the slope. The project is planned for construction in 2014.
CONSEQUENCE OF NEGATIVE ACTION:
Delay in approving the project will result in a delay of design, construction, and repair of the wingwalls. Without
repair of the wingwalls the road could be compromised.
CHILDREN'S IMPACT STATEMENT:
Not applicable.
ATTACHMENTS
Wingwall Att