HomeMy WebLinkAboutMINUTES - 10012013 - C.03RECOMMENDATION(S):
ADOPT Resolution No. 2013/375 accepting as complete the contracted work performed by VSS International, Inc.
for the 2013 Rodeo Terminal Blend Cape Seal project, as recommended by the Public Works Director, Rodeo area.
Project No. 0672-6U2181-13
FISCAL IMPACT:
Project was funded by 92% Proposition 1B Funds and 8% Local Road Funds.
BACKGROUND:
The Public Works Director reports that said work has been inspected and complies with the approved plans, special
provisions and standard specifications and recommends its acceptance as complete as of September 10, 2013.
CONSEQUENCE OF NEGATIVE ACTION:
The contractor will not be paid and acceptance notification will not be recorded.
CHILDREN'S IMPACT STATEMENT:
Not applicable.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 10/01/2013 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Candace Andersen, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
ABSENT:Federal D. Glover, District V
Supervisor
Contact: Kevin Emigh, 925-313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: October 1, 2013
David Twa, County Administrator and Clerk of the Board of Supervisors
By: Stacey M. Boyd, Deputy
cc:
C. 3
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:October 1, 2013
Contra
Costa
County
Subject:ACCEPTANCE and Giving Notice of Completion of Contract for the 2013 Rodeo Terminal Blend Cape Seal, Rodeo
area.
ATTACHMENTS
Resolution No.
2013/375