HomeMy WebLinkAboutMINUTES - 01141986 - T.4 THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
Adopted this Order on January 14, 1986 by the following vote:
AYES: Supervisors Fanden, Schroder, McPeak, Torlakson, ,Powers
NOES: None
ABSENT: None
ABSTAIN: None RESOLUTION NO. 86/ 22
SUBJECT: Certification of the Environmental Impact Report and Approval of the
Upper Pine Creek Flood Control Project. Concord-Walnut Creek Area.
Project No. 7520-6B8294.
The Board of Supervisors of Contra Costa County as the Governing Board
of the Contra Costa County Flood Control District RESOLVES that:
On January 7 , 1986, the Board of Supervisors formally received the
environmental documents for the Upper Pine Creek Flood Control Project and set
January 14, 1986, at 10:30 for a public hearing on the project. At said hearing
the following persons addressed the Board:
Cheryl Wong-Ng, 2975 Lane Drive, Concord
Clifton Wilson, 2915 Lane Drive, Concord
The Chief Engineer recommended that the Board approve the project with
the earth flood plain channel and that the Board adopt the findings and- proposed
mitigation measures presented in County Planning Commission Resolution No. 66-1985.
The Board hereby CERTIFIES that the Environmental Impact Report,
submitted to it by the Flood Control District, as to the environmental impact of
the Upper Pine Creek Flood Control Project, has been completed in compliance with
the California Environmental Quality Act, and it has reviewed and considered the
information contained therein. This Board ACKNOWLEDGES that the project would
have certain environmental effects and ADOPTS the findings and mitigation measures
expressed in Planning Commission Resolution No. 66-1985 which mitigate those
- effects.
The Board hereby APPROVES the project and DIRECTS the Chief Engineer to
commence acquisition of the various rights of -way needed for the project and to
- file with the County Clerk 'a Notice of Determination for this project.
Also REQUESTED the Public Works Director to report on options available
to the County relative -to disposition of the property in the Pine Creek Detention
Basin area.
MFK:bb
BO:UpPine.Adopt.tl2
Orig. Dept: Public Works Department
Flood Control Planning
cc: County Administrator I hereby certify that this is a true and correct copy of
Community Development an action taken and entered on the minutes of the
County Counsel Board of Supervisors on the date shown.
Public Works Director ATTESTED: � /6 /'y5_/0Flood Control Planning PHIL BA CCHELOR, ierk of the Board
City of Walnut Creek
1666 N. Main Street of Supervisors and County Administrator
Walnut Creek, CA 94596
City of Concord By , Deputy
1950 Parkside Drive
Concord, CA 94519
bb
RESOLUTION 86/ 22