HomeMy WebLinkAboutRESOLUTIONS - 02082022 - 2022/44RESOLUTION NO. 2022/44
ATTACHMENT A
Re: Request to the Metropolitan Transportation Commission for the Allocation of Fiscal Year 2022/2023
Transportation Development Act Article 3 Pedestrian/Bicycle Project Funding
FINDINGS
1. That Contra Costa County is not legally impeded from submitting a request to the Metropolitan Transportation
Commission for the allocation of Transportation Development Act (TDA) Article 3 funds, nor is Contra Costa
County legally impeded from undertaking the project(s) described in “Attachment B” of this resolution.
2. That Contra Costa County has committed adequate staffing resources to complete the project(s) described in
Attachment B.
3. A review of the project(s) described in Attachment B has resulted in the consideration of all pertinent matters,
including those related to environmental and right-of-way permits and clearances, attendant to the successful
completion of the project(s).
4. Issues attendant to securing environmental and right of way permits and clearances for the projects described in
Attachment B have been reviewed and will be concluded in a manner and on a schedule that will not jeopardize
the deadline for the use of the TDA funds being requested.
5. That the project(s) described in Attachment B comply with the requirements of the California Environmental
Quality Act (CEQA, Public Resources Code Sections 21000 et seq.).
6. That as portrayed in the budgetary description(s) of the project(s) in Attachment B, the sources of funding other
than TDA are assured and adequate for completion of the project(s).
7. That the project(s) described in Attachment B are for capital construction and/or final design and engineering or
quick build project; and/or for the maintenance of a Class I bikeway which is closed to motorized traffic and/or
Class IV separated bikeway; and/or for the purposes of restriping Class II bicycle lanes; and/or for the
development or support of a bicycle safety education program; and/or for the development of a comprehensive
bicycle and/or pedestrian facilities plan, and an allocation of TDA Article 3 funding for such a plan has not
been received by Contra Costa County within the prior five fiscal years.
8. That the project(s) described in Attachment B which are bicycle projects have been included in a detailed
bicycle circulation element included in an adopted general plan, or included in an adopted comprehensive
bikeway plan (such as outlined in Section 2377 of the California Bikeways Act, Streets and Highways Code
section 2370 et seq.) or responds to an immediate community need, such as a quick-build project.
9. That any project described in Attachment B bicycle project meets the mandatory minimum safety design criteria
published in the California Highway Design Manual or is in a National Association of City and Transportation
Officials (NACTO) guidance or similar best practices document.
10. That the project(s) described in Attachment B will be completed in the allocated time (fiscal year of allocation
plus two additional fiscal years).
11. That Contra Costa County agrees to maintain, or provide for the maintenance of, the project(s) and facilities
described in Attachment B, for the benefit of and use by the public.
MTC Programming and Allocations Section April 2021 TDA Article 3 Model Resolution Page 1
Resolution No. 2022/44
Attachment B
page 1 of 1
TDA Article 3 Project Application Form
Fiscal Year of this Claim: 2022/2023 Applicant: Contra Costa County Public Works
Contact person: Jeff Valeros
Mailing Address: 255 Glacier Drive, Martinez, CA 94553
E-Mail Address: jeff.valeros@pw.cccounty.us Telephone: 925-313-2031
Secondary Contact (in event primary not available): Austin Pato
E-Mail Address: Austin.pato@pw.cccounty.us Telephone: 925-313-2378
Project Title (Short Description): Livorna Road Shoulder Widening
Amount of claim: $100,000
Description of Overall Project:
Project Scope Proposed for Funding: (Project level environmental, preliminary planning, and ROW are ineligible uses of TDA funds.)
Project Budget and Schedule
Project Eligibility: YES?/NO?
A. Has the project been approved by the claimant's governing body? (If "NO," provide the approximate date approval is
anticipated). February 8, 2022
PENDING
B. Has this project previously received TDA Article 3 funding? If "YES," provide an explanation on a separate page. NO
C. For "bikeways," does the project meet Caltrans minimum safety design criteria pursuant to Chapter 1000 of the California
Highway Design Manual? (Available on the internet via: http://www.dot.ca.gov).
YES
D. Has the project been reviewed by the Bicycle and Pedestrian Advisory Committee? (If "NO," provide an explanation).
December 13, 2021
YES
E. Has the public availability of the environmental compliance documentation for the project (pursuant to CEQA) been
evidenced by the dated stamping of the document by the county clerk or county recorder? (required only for projects that
include construction).
PENDING
F. Will the project be completed before the allocation expires? Enter the anticipated completion date of project (month and
year) June 2024
YES
G. Have provisions been made by the claimant to maintain the project or facility, or has the claimant arranged for such
maintenance by another agency? (If an agency other than the Claimant is to maintain the facility provide its name:
)
YES
Project
Phase TDA 3 Other Funds Total Cost
Estimated Completion
(month/year)
Bike/Ped
Plan -
ENV - 01/2022
PA&ED 25,000 25,000 06/2023
PS&E 10,000 35,000 45,000 12/2023
ROW -
CON 90,000 90,000 06/2024
Total Cost 100,000 60,000 160,000
This project will widen the roadway shoulder on a 200-ft segment of Livorna Road in unincorporated Alamo. This shoulder widening
will allow space for bicyclists and will complete the bicycle connectivity on Livorna Road from I-680 to the County boundary line (1.6
miles).
Engineering and Construction.