HomeMy WebLinkAboutMINUTES - 07092013 - C.87RECOMMENDATION(S):
APPROVE the work plan and timeline for developing the Measure WW expenditure plan for the unincorporated
areas of the County, and AUTHORIZE an allocation not to exceed $60,000 in Park Impact Fees collected within the
unincorporated areas of the County to help pay staff costs associated with developing the proposed expenditure plan
and submitting it to the East Bay Regional Park District by March 2014.
FISCAL IMPACT:
Park Impact Fees collected in the unincorporated County will be used to pay for costs associated with developing a
list of projects to be submitted to the East Bay Regional Park District for approval.
BACKGROUND:
In 2008, voters approved the East Bay Regional Park District’s (EBRPD) Measure WW Park Bond Extension that
provides funding for high priority community park projects. A total of $7.93 million is allocated to areas within the
unincorporated area of the County. These funds were allocated to Recreation and Park Districts and Community
Service Districts ($2.39 million), specific County Services Areas ($2.49 million), and to unincorporated areas not in a
CSA or CSD district ($3.05 million). All Measure WW funds must be fully expended by December 2018.
Pursuant to the Measure WW, the projects must meet the following standards:
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 07/09/2013 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Candace Andersen, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Bob Calkins, (925)
674-7877
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: July 9, 2013
David Twa, County Administrator and Clerk of the Board of Supervisors
By: June McHuen, Deputy
cc: Public Works Director
C. 87
To:Board of Supervisors
From:Transportation, Water & Infrastructure Committee
Date:July 9, 2013
Contra
Costa
County
Subject:Proposed Work Plan for Allocating Measure WW Funds in the Unincorporated County Areas
BACKGROUND: (CONT'D)
Insure equitable geographic distribution of the funds.
Use of the property/facilities must be for at least 25 years.
Provide lands and facilities for recreational activities and services and historic preservation. Capital projects
may include acquisition of park land and development of recreational facilities, including renovation of existing
facilities.
Public art projects are eligible as long as they are in or adjacent to a parks and recreation facility.
The Task/Timeline chart (Attachment A) outlines the proposed work plan for developing a list of projects to be
submitted to East Bay Regional Park District (EBRPD) for approval for areas in the unincorporated County not
in a CSA or CSD. Depending on the specific task, the Department of Conservation and Development (DCD)
and/or Public Works (PW) will take lead responsibility for ensuring the task is completed within the specified
time frame.
CONSEQUENCE OF NEGATIVE ACTION:
Without Board approval, the process for developing the list of projects to be submitted to East Bay Regional Park
District by the March 2014 deadline would be delayed by at least a year, therefore possibly jeopardizing the
County's ability to spend the funds by the December 2018 deadline.
CHILDREN'S IMPACT STATEMENT:
The park and recreation projects ultimately identified through this process will support the following outcomes in
the Children's Report Card: 1) Children and youth are healthy and preparing for productive adulthood; and 2)
Communities are safe and provide a high quality of life for children and families
ATTACHMENTS
Attachment A - Proposed Work Plan / Timeline
ATTACHMENT A
PROPOSED WORK PLAN AND TIMELINE
MEASURE WW FUNDS TO BE ALLOCATED IN THE UNINCORPORATED COUNTY
Task Lead
Department
Timeline
1. Obtain approval from Transportation, Water, and
Infrastructure Committee (TWIC) and Board of Supervisors
of the proposed work plan.
DCD June 2013
2. Inventory, survey and assess existing parks in the
unincorporated areas.
DCD July – August 2013
3. Meet with each Supervisor to discuss potential projects
within their District, and identify other potential stakeholders.
DCD August 2013
4. Meet with the East Bay Regional Park District (EBRPD) to
obtain their ideas on high priority park projects in the
unincorporated areas of the County.
DCD August 2013
5. Plan, coordinate and conduct meetings with various
stakeholders to get their thoughts and ideas on potential
projects.
DCD August – September
2013
6. Develop list of potential projects based on the results of the
stakeholder meetings.
DCD October 2013
7. Develop initial cost estimates for each potential project
identified through the meeting with stakeholders, including
evaluating maintenance mechanisms to support each
proposed project.
PW November –
December 2013
8. Plan, coordinate and conduct follow-up meetings with
stakeholders to review/prioritize list of projects. Obtain
approval of the final project list from the TWIC and Board of
Supervisors.
DCD/PW January – February
2014
9. Submit project list/application to EBRPD for approval. DCD/PW March 2014
10. Plan, design, and manage construction of approved projects. PW June 2014 -