HomeMy WebLinkAboutMINUTES - 02262013 - C.02RECOMMENDATION(S):
ADOPT Resolution No. 2013/93 accepting as complete the contracted work performed by Bruce Carone Paving &
Grading, Inc., for the Willow Pass Road Safety Improvements - Phase 2 project, as recommended by the Public
Works Director, Bay Point area. Project No. 0662-6R4056-12
FISCAL IMPACT:
Project was funded by 86.6% Proposition 1B funds and 13.4% Transportation Development Act funds.
BACKGROUND:
The Public Works Director reports that said work has been inspected and complies with the approved plans, special
provisions and standard specifications and recommends its acceptance as complete as of January 31, 2013.
CONSEQUENCE OF NEGATIVE ACTION:
The contractor will not be paid and acceptance notification will not be recorded.
CHILDREN'S IMPACT STATEMENT:
Not applicable.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 02/26/2013 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Candace Andersen, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Kevin
Emigh,925-313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: February 26, 2013
David Twa, County Administrator and Clerk of the Board of Supervisors
By: STACEY M. BOYD, Deputy
cc: J. Dowling, Design/Construction, S. Reed, Design/Construction, P. Denison, Finance
C. 2
To:Board of Supervisors
From:Julia R. Bueren, Public Works
Date:February 26, 2013
Contra
Costa
County
Subject:ACCEPTANCE & Giving Notice of Completion of Contract for the Willow Pass Road Safety Improvements- Phase