HomeMy WebLinkAboutMINUTES - 02122013 - C.07RECOMMENDATION(S):
APPROVE the Arlington Avenue Curb Ramp project contingency fund increase of $6,000, for a new contingency
fund total of $21,200, and new payment limit of $173,202, effective February 12, 2013; and
ADOPT Resolution No. 2013/83 accepting as complete the contracted work performed by Sposeto Engineering, Inc.
for the Arlington Avenue Curb Ramp project, as recommended by the Public Works Director,Kensington area.
(Project No. 0662-6R4207)
FISCAL IMPACT:
Project was funded by 100% Local Road funds.
BACKGROUND:
The contingency fund increase is necessary to compensate the contractor for required extra work. The Public Works
Director reports that said work has been inspected and complies with the approved plans, special provisions and
standard specifications and recommends its acceptance as complete as of February 1, 2013.
CONSEQUENCE OF NEGATIVE ACTION:
The contractor will not be paid and acceptance notification will not be recorded.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 02/12/2013 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
Contact: Kevin Emigh,
925-313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: February 12, 2013
David Twa, County Administrator and Clerk of the Board of Supervisors
By: , Deputy
cc: J. Dowling, S. Reed, P. Denison
C. 7
To:Board of Supervisors
From:Julia R. Bueren, Public Works
Date:February 12, 2013
Contra
Costa
County
Subject:Increase Contingency Fund and ACCEPTANCE & Giving Notice of Completion of Contract - Arlington Avenue
Curb Ramp Project, Kensington area.
CHILDREN'S IMPACT STATEMENT:
Not applicable.
CLERK'S ADDENDUM
RELISTED to a future date uncertain.
ATTACHMENTS
Resolution No. 2013/83
Recorded at the request of:Clerk of the Board
Return To:Public Works Department, Design/Construction Division
THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
and for Special Districts, Agencies and Authorities Governed by the Board
Adopted this Resolution on 02/12/2013 by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
RECUSE:
Resolution No. 2013/83
In the Matter of Accepting and Giving Notice of Completion of Contract for the Arlington Avenue Curb Ramp project,
Kensington area, Project No. 0662-6R4207.
WHEREAS the Board of Supervisors of Contra Costa County RESOLVES that on August 21, 2012, the County contracted with
Sposeto Engineering, Inc. for the work generally consisting of removing existing curb, sidewalk, traffic stripes and pavement
markings, constructing new curb, sidewalk, curb ramps, retaining walls in compliance with the Americans with Disabilities Act,
and placing new traffic stripes and pavement markings in the Kensington area, with The Gray Insurance Company as surety, for
work to be performed on the grounds of the County; and
The Public Works Director reports that said work has been inspected and complies with the approved plans, special provisions
and standard specifications and recommends its acceptance as complete as of February 1, 2013.
NOW, THEREFORE, BE IT RESOLVED that said work is ACCEPTED as complete on said date, and the Clerk shall file with
the County Recorder a copy of this resolution and Notice as a Notice of Completion for said contract.
Contact: Kevin Emigh, 925-313-2233
I hereby certify that this is a true and correct copy of an action taken and
entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED: February 12, 2013
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: , Deputy
cc: J. Dowling, S. Reed, P. Denison