HomeMy WebLinkAboutMINUTES - 10162012 - C.17RECOMMENDATION(S):
ADOPT Resolution No. 2012/435 accepting as complete the contracted work performed by Ghilotti Bros., Inc., for
the Buchanan Field Airport Runway 1L-19R Rehabilitation project, as recommended by the Public Works Director,
Concord area. Project No. 4855-4690-SAS-6X5381
FISCAL IMPACT:
The project construction was funded by 100% Federal FAA AIP funds.
BACKGROUND:
The Public Works Director reports that said work has been inspected and complies with the approved plans, special
provisions and standard specifications and recommends its acceptance as complete as of September 19, 2012.
CONSEQUENCE OF NEGATIVE ACTION:
The contractor will not be paid and acceptance notification will not be recorded.
CHILDREN'S IMPACT STATEMENT:
Not applicable.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 10/16/2012 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Candace Andersen, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
ABSENT:Federal D. Glover, District V
Supervisor
Contact: Kevin Emigh, (925)
313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors
on the date shown.
ATTESTED: October 16, 2012
David Twa, County Administrator and Clerk of the Board of Supervisors
By: Carrie Del Bonta, Deputy
cc: J. Dowling, Design/Construction, P. Denison, Finance, S. Reed, Design/Construction
C. 17
To:Board of Supervisors
From:Julia R. Bueren, Public Works
Date:October 16, 2012
Contra
Costa
County
Subject:ACCEPTANCE & Giving Notice of Completion of Contract for the Buchanan Field Airport Runway 1L-19R
Rehabilitation, Concord area.
ATTACHMENTS
Resolution No.
2012/435