HomeMy WebLinkAboutMINUTES - 10122012 - C.04RECOMMENDATION(S):
APPROVE the Right of Way Contract and APPROVE and ACCEPT the Grant of Maintenance and Access
Easement dated September 20, 2012 from the East Bay Regional Park District (District) and ACCEPT the Grant
Deed dated September 20, 2012 from the District for property rights needed in connection with the Vasco Road
Safety Improvements Project-Phase 2 (Project). Project No. 0662-6R4255-10.
AUTHORIZE Public Works Director or designee to execute said Right of Way Contract and Grant of Maintenance
and Access Easement on behalf of the County.
APPROVE payment of $25,000 for said property rights and AUTHORIZE the Auditor-Controller to issue a check in
said amount payable to Fidelity National Title Company (Title Company), 191 Sand Creek Road, Suite 160,
Brentwood, California 94513 Escrow No. 10-332461-DH to be forwarded to the Real Estate Division for delivery.
DIRECT the Real Estate Division to have the above referenced Grant Deed and Grant of Maintenance and Access
Easement delivered to the Title Company for recording in the Office of the County Recorder.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 10/16/2012 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Candace Andersen, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
ABSENT:Federal D. Glover, District V
Supervisor
Contact: Michele Trecek, 925
313-2010
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors
on the date shown.
ATTESTED: October 16, 2012
David Twa, County Administrator and Clerk of the Board of Supervisors
By: STACEY M. BOYD, Deputy
cc: J. Carlson, Real Estate, Auditor-Controller, County Recorder, Neil Leary, Design, Cris Lau, Transportation Eng., Lisa Mangabay, Finance
C. 4
To:Board of Supervisors
From:Julia R. Bueren, Public Works
Date:October 16, 2012
Contra
Costa
County
Subject:Vasco Road Safety Improvements Project-Phase 2.
FISCAL IMPACT:
Funded by 100% Local Road Funds.
BACKGROUND:
These property rights are required for the Vasco Road Safety Improvements Project-Phase 2 in accordance with
the approved plans and specifications for that project. The property and interests in property being acquired
include five (5) fee parcels and six (6) easement parcels.
The Board previously adopted a Mitigated Negative Declaration and Mitigation Monitoring Program for this
activity on August 25, 2009.
CONSEQUENCE OF NEGATIVE ACTION:
The project will not have sufficient land rights to allow construction in accordance with the approved plans and
specifications.
CHILDREN'S IMPACT STATEMENT:
Not applicable.
ATTACHMENTS
Grant Deed
Grant of Maintenance and Access Easement
Right of Way Contract