HomeMy WebLinkAboutMINUTES - 06052012 - C.22RECOMMENDATION(S):
ADOPT Resolution No. 2012/253 accepting completion of improvements and completion of warranty period for the
Marsh Creek Fish Passage Improvement Project developed by American Rivers, Inc., a nonprofit corporation
organized and existing under the laws of the District of Columbia, as recommended by the Chief Engineer, Flood
Control and Water Conservation District, Brentwood area. (100% Flood Control Zone 1 Funds)
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
American Rivers has completed the improvements in accordance with the Funding Agreement for the Marsh Creek
Fish Passage Improvement Project and in accordance with the Flood Control Permit 609-10.
CONSEQUENCE OF NEGATIVE ACTION:
The completion of improvements will not be accepted and the surety bond will not be exonerated.
CHILDREN'S IMPACT STATEMENT:
Not applicable.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 06/05/2012 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Teri E. Rie (925)
313-2363
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: June 5, 2012
David Twa, County Administrator and Clerk of the Board of Supervisors
By: STACEY M. BOYD, Deputy
cc: Teri E. Rie, Flood Control, Catherine Windham, Flood Control, Renee Hutchins, Records, Luke Hunt, American Rivers
C. 22
To:Contra Costa County Flood Control District Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:June 5, 2012
Contra
Costa
County
Subject:Adopt Resolution accepting completion of improvements and warranty period for the Marsh Creek Fish Passage
Improvement Project. Project #7521-6D8449
ATTACHMENTS
Resolution No.
2012/253