HomeMy WebLinkAboutMINUTES - 06052012 - C.12RECOMMENDATION(S):
ADOPT Resolution No. 2012/248 to APPROVE the second extension of the Subdivision Agreement for SD
99-08356 for a project being developed by Jilma Graves, El Sobrante area.
FISCAL IMPACT:
No Fiscal Impact.
BACKGROUND:
The Subdivision Agreement needs to be renewed as the improvements are not completed yet. (Approximately 90% of
the work has been completed to date.) The developer has requested additional time to complete improvements.
Granting an extension gives the developer an additional year to complete the improvements and keeps the bonding
current.
CONSEQUENCE OF NEGATIVE ACTION:
The Subdivision Agreement will not be renewed if the extension is not granted; the developer cannot complete the
improvements; the bonds cannot be kept current; and, the County may need to foreclose on the developer's bonds and
complete the improvements.
CHILDREN'S IMPACT STATEMENT:
Not applicable.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 06/05/2012 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: John Capozzo,
925-313-2352
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: June 5, 2012
David Twa, County Administrator and Clerk of the Board of Supervisors
By: STACEY M. BOYD, Deputy
cc: J. LaRocque, Land Developement, S. Reed, Construction, J. Capozzo, Engineering Services, C. Sumpter, Current Planning DCD
C. 12
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:June 5, 2012
Contra
Costa
County
Subject:APPROVE the second extension of the Subdivision Agreement for Subdivision 99-08356, El Sobrante area.
ATTACHMENTS
Resolution No.
2012/248
Agreement Extension
Continuation Certificate