HomeMy WebLinkAboutMINUTES - 02251986 - X.5 x �
THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
Adopted this Order on February 25, 1986 by the following vote:
AYES: Supervisors Fanden, Schroder, McPeak, Torlakson & Powers
NOES : None
ABSENT: None
ABSTAIN: None
SUBJECT: In the Matter of Award of Contract for San Pablo Dam Road Slide
at Sta. 250, Project No. 0671-6R6717-83, Orinda Area.
Bidder Total Amount Bond Amounts
Kulchin & Associates, Inc. $194,850.00 Payment $97,475.00
PO Box 151 Faith. Perf. $194,850.00
South San Francisco, CA 94080
Soil Engineering Construction, Inc.
William P. Young, Inc.
Messa Construction Co.
Schnabel Foundation Company
Brudigam Construction, Inc.
J. H. Pomeroy & Co. , Inc.
Ross Bros. Construction, Inc.
Benco Construction and Engineering, Inc.
0. C. Jones & Sons
Pleasanton Engineering Contractors
R. L. Davis Construction Co. , Inc.
R. M. Harris Co.
M.T.L. Construction Co. , Inc.
Valentine Corporation
M & M Drilling
Power-Anderson, Inc.
The above-captioned project and the specifications therefor being
approved, bids being duly invited and received by the Public Works Director;
and
The Public Works Director recommending that the bid listed first
above is the lowest responsible bid and this Board concurring and so
finding;
IT IS BY THE BOARD ORDERED, that the contract for the furnishing
of labor and materials for said work is awarded to said first listed
bidder at the listed amount and at the unit prices submitted in said
bid; and that said contractor shall present two good and sufficient surety
bonds as indicated above; and that the Public Works Department shall
prepare the contract therefor.
IT IS FURTHER ORDERED that, after the contractor has signed the
contract and returned it together with bonds as noted above and any required
certificates of insurance or other required documents, and the Public
Works Director has reviewed and found them to be sufficient, the Public
Works Director is authorized to sign the contract for this Board.
IT IS FURTHER ORDERED that, in accordance with the project specifica-
tions and/or upon signature of the contract by the Public Works Director,
any bid bonds posted by the bidders are to be exonerated and any checks or
cash submitted for bid security shall be returned.
Orig.Dept.: Public Works Department (D/C) ihereby cerlifytha,ihisisatrue and correct copy of
an action taken and entcrad on the r..Inutes of the
Board of Supervisors on the date shown.
cc: County Administrator ATTESTED: FEB 2 .9 mqs
Auditor-Controller PHIL BATCHELOR, C'erk of the Saa;d
P. W. Accounting
Contractor of Supervisora and County"-Idmiristrator
Award.S P.t4 By �M� . Deputy