HomeMy WebLinkAboutMINUTES - 04242012 - C.51RECOMMENDATION(S):
AUTHORIZE the Chair of the Board to send the attached letter to the state requesting levee improvement funding for
three specific projects, as recommended by the Transportation, Water and Infrastructure Committee.
FISCAL IMPACT:
NONE to the County. If the state provides the requested grant funding, the required matching funds will be provided
by the Contra Costa Water District, East Bay Municipal Utility District, and other water providers elsewhere in the
state.
BACKGROUND:
In January a group of seven urban water agencies, including the Contra Costa Water District (CCWD) and East Bay
Municipal Utility District (EBMUD), requested state funding for three major levee improvement projects that would
increase the reliability of water supply and help protect Delta lands from flooding by reducing the chances of levee
breaks. Two of the three projects would directly benefit Contra Costa residents and businesses by shoring up levees
that protect the CCWD and EBMUD water supply channels, and by converting an existing CCWD open canal into a
pipeline
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 04/24/2012 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
ABSENT:Gayle B. Uilkema, District II
Supervisor
Contact: John Greitzer, 674-7824
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: April 24, 2012
David Twa, County Administrator and Clerk of the Board of Supervisors
By: June McHuen, Deputy
cc:
C. 51
To:Board of Supervisors
From:Transportation, Water and Infrastructure Comm
Date:April 24, 2012
Contra
Costa
County
Subject:Request for state funds for levee improvements
BACKGROUND: (CONT'D)
near Rock Slough in the Oakley area. The third project would improve levees along a portion of Middle River,
which feeds the export pumps in the South Delta that are used to pump water to the South Bay, Central Valley,
and Southern California.
The Transportation, Water and Infrastructure Committee discussed the water agencies' funding request on April
5. The Committee recommends the Board authorize the Chair to sign the attached letter of suppport to the state,
urging the state to provide the requested funding.
Also attached is the joint letter from the seven urban water agencies, which requests funds from the state and
provides details about the three projects.
CONSEQUENCE OF NEGATIVE ACTION:
Support from the County may help persuade the state to provide funding for the three projects, which are critical
to protecting Contra Costa's water supply and protecting Delta lands from flooding. Without such support from
the County, there is no additional impetus for the state to provide the funds other than the request letter they have
received from the water districts.
CHILDREN'S IMPACT STATEMENT:
NONE.
ATTACHMENTS
water districts funding request
letter of support
January 4, 2012
John Laird, Secretary
Natural Resources Agency
1416 Ninth Street
Sacramento, CA 95814
Dear Secretary Laird:
Representing six Bay Area water agencies and the Metropolitan Water District, we are
writing to request your assistance in our collaborative effort to improve water supply
reliability in the Delta. While our agencies may have different perspectives on some of
the many complex issues in the Delta, we all recognize the importance of continuing to
maintain and improve the Delta levee system both in the near term and in the decades to
come.
As part of our collaborative discussions about near term Delta actions, we have
developed a paper entitled, “Urban Water Agencies Strategy for Delta Levees – List of
Priority Levee Projects” enclosed for your consideration. The three projects described in
the paper meet the criteria for “Early Actions” in the emerging Delta Plan and in the Bay
Delta Conservation Plan, and reflect a “no regrets” approach to infrastructure investment.
In particular, we believe these projects qualify for funding from Proposition 1E, and
encourage you to consider full implementation to enhance water supply reliability and the
general resilience of the Delta. In total, the funding need for the three levee projects
ranges up to $163 million.
Secretary John Laird
January 4, 2012
Page 2
We appreciate your attention to these priority projects, and will call your office to arrange
a meeting to discuss the best approach to addressing this urgent need.
Sincerely,
Jerry Brown, General Manager
Contra Costa Water District
Michael Carlin, Deputy General Manager
San Francisco Public Utilities Commission
Alexander R. Coate, General Manager
East Bay Municipal Utility District
Jill Duerig, General Manager
Zone 7 Water Agency
Alameda County Flood Control & Water Conservation District
Secretary John Laird
January 4, 2012
Page 3
Beau Goldie, Chief Executive Officer
Santa Clara Valley Water District
Jeff Kightlinger, General Manager
Metropolitan Water District of Southern California
Walt Wadlow, General Manager
Alameda County Water District
ARC:DW
Enclosure
cc: Gerald Meral, Deputy Secretary, Natural Resources Agency
Mark Cowin, Director, Department of Water Resources
Charlton Bonham, Director, Department of Fish and Game
State Water Resources Control Board
Delta Stewardship Council
Members of the California Legislature
Draft 12-30-2011 v5
4
DRAFT
URBAN WATER AGENCIES STRATEGY FOR DELTA LEVEES
LIST OF PRIORITY LEVEE PROJECTS
Urban Water Agencies have identified the need for a strategy to strengthen the integrity of the
Sacramento/San Joaquin Delta (Delta) Levee system for reliable water supplies and water
quality. The projects identified should be implemented on a short-term basis to provide benefits
in a timely manner.
CATEGORIES OF SUPPORTED LEVEE IMPROVEMENT PROJECTS
Urban Water Users reliant on the Delta levee system support levee improvement projects to (1)
protect water supply interests reliant on Delta levees, and (2) improve protections for other uses
including but not limited to life, property, infrastructure and ecosystem habitats in the Delta.
Protection to Water Supply Interests Reliant on Delta Supplies
• Protect water supply infrastructure
• Provide freshwater pathway conveyance under emergency conditions
• Reduce risk of levee failure on islands that would have the greatest negative water quality
impact at drinking water intakes (e.g. eight western Delta islands)
• Reduce salinity at water supply intakes and enhance operational flexibility (e.g. tidal
marsh restoration in north and west Delta and marsh regions by levee breaching).
Protection of Life, Property, Infrastructure and Habitats in the Delta
• Protect urban areas
• Protect infrastructure (highways, power lines, railways, etc.)
• Habitat restoration projects important to water users reliant on the Delta
The remainder of this paper focuses on ongoing projects to protect water supply. As illustrated in
Figure 1, levee improvements to protect existing infrastructure and provide a freshwater pathway
overlap in many areas.
SPECIFIC LEVEE IMPROVEMENT ACTIONS
The following list of levee improvement actions should be implemented on a short-term basis to
protect water quality and supplies of interests reliant on the Delta levee system. These actions
are both consistent with protection of existing water supply infrastructure and compatible with
dual conveyance options under consideration by the Bay Delta Conservation Plan. The list of
actions is based on the general categories of need described above. Relevant information
includes name, description, benefits, approximate cost, status of funding and implementation
stage.
5
Protection to Water Supply Interests Reliant on Delta Supplies
Protection of water supply infrastructure is essential during and following a major seismic or
flood event. Freshwater flows in the Delta must be protected and quickly restored following
seismic and flood emergencies, and levees supporting critical water conveyance facilities must
be fortified. Stockpiling of emergency response materials for repairs at key locations in the
Delta can facilitate protection of critical infrastructure and restoration of freshwater supplies after
emergencies in a timely manner. The following specific actions are identified:
Name: Mokelumne Aqueduct Levee Enhancements
Description: Reduce the potential for levee failure by improving the level of flood protection
afforded by various levees in the south Delta vital to the protection of the Mokelumne
Aqueduct. Levees to be improved to provide added protection are:
• Lower Roberts Island
• Lower Jones Tract
• Upper Jones Tract
• Woodward Island
• Palm-Orwood Tract
Benefits: Enhanced protection for water supply afforded by the Mokelumne Aqueduct with
additional benefits to the other infrastructure and lands, including Highway 4, railroads, gas
pipelines/fields and agricultural lands. Improve protection to water supply aqueducts
crossing the Delta, including design and construction of emergency interties for interim
supplies to aqueducts. Study relocation of the water supply aqueducts for continuation of
reliable water service for public health and safety after a catastrophic levee failure.
Approximate Cost: $83 million (Prop 1E)
Status of Funding: Of the $83 million cited above, for five islands that the Mokelumne
Aqueducts cross, about $35 million of that need was addressed by SBx2 1 (Prop 1E) and the
balance of $48 million is the remaining need.
Implementation Stage: Of the $35 million appropriated, about $20 million plus a local cost
share has been fully authorized, cleared CEQA and awarded. The remaining $15 million is
expected to clear those steps in late 2011 or early 2012 for the next construction season.
Name: Contra Costa Canal Levee Elimination and Flood Protection Project
Description: Replace 4 miles of the unlined canal with a pipe (from Rock Slough to CCWD
PP1), eliminating 8 miles of aging levee embankments.
Benefits: Improve CCWD’s water supply reliability while reducing flooding risk to nearby
developments and providing the opportunity for habitat restoration. Under an agreement
with DWR and a CEQA mitigation commitment, the canal must be replaced along the
6
restoration site before the Dutch Slough restoration project can proceed due to likely seepage
from flooding of adjacent islands.
• Dutch Slough restoration project is a potential habitat restoration project under BDCP
(and may be used to partially satisfy the 2008 FWS OCAP requirement).
• Seepage from the Dutch Slough restoration would make it difficult for the SWP and CVP
to meet the D-1641 requirements at Rock Slough; replacing the canal with a pipe will
mitigate for seepage.
Approximate Cost: Approximately $100 million remaining construction costs. All planning
and environmental work is complete.
Status of Funding: $10 million (Prop 1E) grant with $10 million match. Unmet obligation is
approximately $80 million.
Implementation Stage: Phase 1 construction was completed in 2010. Next phase will
commence with current Prop 1E grant, but additional funding is needed.
Name: Middle River Emergency Freshwater Pathway
Description: Restoration of levees to convey freshwater along Middle River and Victoria
Canal to export facilities following a major emergency in the Delta. Middle River levees toe
berms would be provided in advance of an emergency. Stockpiling materials in advance will
facilitate pathway restoration. The pathway supports implementation of DWR’s Delta Flood
Emergency Preparedness, Response and Recovery Program.
Toe berms are proposed on the following segments of the freshwater pathway:
• Bacon Island (east levee)
• Woodward Island (east levee)
• Upper and Lower Jones Tract (west levees)
• McDonald Tract (west levee along Mildred Island)
• Victoria Island (east levee)
The following levee segments form the southern portion of the freshwater pathway, however
toe berms are not proposed:
• Victoria Island (south levee)
• Union Island (north levee)
Levee improvements along the east and west levees of a potential emergency freshwater
pathway are being implemented by local reclamation districts, including landside slope work,
landside toe berms and setback levees at Woodward Island, Upper Jones Tract and Lower
Jones Tract (see Delta Stewardship Council website). Landside toe berms are also being
evaluated and implemented along the west levee of Middle River at Bacon Island by the
reclamation district and through the Corps levee stability program. These improvements are
7
being evaluated to determine compatibility with landside toe berms to reduce levee slumping
in a seismic event, which could reduce estimated costs shown below.
Benefits: The benefits include freshwater delivery to 2/3 of Californians within about a 6-
month window in the event of a catastrophic multi-island failure and associated salinity
intrusion in the Delta.
Approximate Cost: Total cost is estimated at $100 million. $60 million is estimated for
levee toe berms along the pathway. $40 million is estimated for remaining stockpiling
materials to facilitate pathway restoration after a major emergency. Corps levee stability
program planning costs for pathway toe berm development are estimated at $2 million,
comprised of state (Prop 1E), Reclamation District (in-kind) and federal (Corps Levee
Stability Program) sources. Updated construction costs are being prepared at this time.
Status of Funding: $10 million (Prop 84) funds were spent for emergency preparedness rock
stockpiles placed in 2007/08. $37 million (Prop 1E) funds has been appropriated (SBX2_1)
for DWR emergency response studies and materials/equipment stockpile purchases. $43
million (Prop 1E) funds have been authorized (but not appropriated) for remaining Delta risk
reduction activities. Total Prop 1E funding appropriated or authorized is $80 million.
Federal funding of toe berm levee improvements under the Corps Levee Stability Program
will be evaluated upon completion of the feasibility study.
Implementation Stage: The project is currently in the feasibility planning stage, although
initial compatible work is underway by DWR/RD agreement at Bacon Island.
Implementation of Risk-Based Analysis of Levee Protection and Standards
Urban Water Agencies strongly encourage implementation of economically-based risk reduction
on an island-by-island basis. This evaluation would take into account that some islands, or
portions of islands, may be converted to habitat that would change how major investments are
considered for levee improvements. Economically-based risk reduction analyses should consider
(1) protection to life, property and infrastructure in the Delta, and (2) protection to water supply
interests reliant on the Delta levee system. This non-proscriptive, risk-based approach to levee
standards should be incorporated into DWR’s Delta Flood Emergency Preparedness, Response
and Recovery Program and the Delta Levees Program.
Long-Term Interests
Implementing these short-term levee improvements strategies and economically-based standards
does not foreclose or promote any future scenario for the Delta. For example, these levee
improvements would be compatible with dual-conveyance improvements and are consistent with
protection of existing state infrastructure.
Remaining Funding under Proposition 1E
The Disaster Preparedness and Flood Protection Bond Act of 2006 (Proposition 1E) authorizes
$4.09 billion in general obligation bonds to rebuild and repair California’s most vulnerable flood
8
control structures to protect homes and prevent loss of life from flood-related disasters, including
levee failures, flash floods, and mudslides and to protect California’s drinking water supply
system by rebuilding delta levees that are vulnerable to earthquakes and storms.
A March 29, 2011 State Proposition Allocation Balance Report, prepared by the Resources
Agency, provides detailed information on remaining balances in Propositions 1E, 84 and 50.
Proposition 1E appears to be the most practical source of significant future funding for Delta
levees. The following table drawn from the March 29, 2011 report provides a comprehensive
assessment of remaining funds in Proposition 1E.
1E
Bond
Program
Public
Resources
Code
1E Bond
Allocation
($000)
Enacted
Expenditure
($000)
Proposed
Expenditure
($000)
Statewide
Bond Costs
($000)
Balance
Remaining
($000)
State Plan
of Flood
Control
5096.821 $3,000,000 ($2,005,928) ($197,403) ($105,000) $691,669
Flood
control and
flood
prevention
projects
5096.824 $500,000 ($103,400) ($60,067) ($17,500) $319,033
Flood
protection
corridors
and
bypasses
5096.825 $290,000 ($186,454) ($37,393) ($10,150) $56,003
Storm water
flood
management
5096.827 $300,000 ($230,408) ($555) ($10,500) $58,537
TOTAL $4,090,000 ($2,526,190) ($295,418) ($143,150) $1,125,242
As of March 2011, Proposition 1E had a remaining balance of approximately $1.13 billion, or
27.5% of the $4.09 billion authorization.
Beneficiaries of Delta Levees
Levee improvement projects in the Delta advocated by urban water agencies offer direct benefits
for protecting water supply and water quality. However, there are numerous other interests and
asset owners that also stand to benefit from the three identified projects. These include, but may
not be limited to:
• State Highway 4 (Caltrans) and local roads
• Shipping channel to Stockton
• Natural gas pipelines and storage fields (Kinder Morgan, PG&E)
• Electrical transmission lines (TANC)
• BNSF railway
• Agriculture
9
• Recreational boating
• Commercial and recreational fishing
At present, most of these users are not contributing financially to levee maintenance and
improvement in the Delta, and any unpaid benefits they receive make them effectively “free
riders”. If a mechanism for implementing the beneficiary pays principle were in place, these
users could be assessed proportional to the benefits they receive from investments to improve the
levees. Establishing such an assessment system would also help to meet the increased non-state
cost share for levee investment envisioned by the Delta Stewardship Council.
In practice however, most of these interests cannot be expected to participate voluntarily with
financial support for the levee projects in question. Further, there is no near-term prospect of a
benefit assessment district or other authorized body that could impose mandatory fees or charges
under a beneficiary pays system. Therefore, the most practical approach for near term funding
the multi-benefit levee projects is to utilize state funding supported by an urban agency cost
share, to be determined.
10