HomeMy WebLinkAboutMINUTES - 04032012 - C.53RECOMMENDATION(S):
1. APPROVE the plans, specifications, and design for Trade Bid Package 7A, consisting of
building signage; and DELEGATE to the Deputy General Services Director, or designee, or
to any licensed architect or engineer employed by the County, the authority to approve any
design modifications prepared for the above project.
2. AWARD a trade contract in the amount of $154,479 to Vomar Products, Inc. (“Vomar”),
the lowest responsive and responsible bidder for Trade Bid Package 7A, consisting of
building signage for the subject project; and DIRECT the Deputy General Services
Director, or designee, to prepare the trade contract.
3. DETERMINE that Turner Construction Company (“Turner”), as the Construction
Manager At-Risk, has documented an adequate good faith effort to comply with the
requirements of the County’s Outreach Program in connection with the above trade contract
and WAIVE any irregularities in such compliance.
4. FURTHER DETERMINE that Vomar, as the lowest responsive and responsible bidder
for the above trade contract, and Turner, as Project Manager, have entered into a Project
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 04/03/2012 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
ABSENT:Gayle B. Uilkema, District II
Supervisor
Contact: Rob Lim (925) 313-7242
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: April 3, 2012
David Twa, County Administrator and Clerk of the Board of Supervisors
By: Carrie Del Bonta, Deputy
cc: GSD Administration, GSD Accounting, GSD CPM Division Manager, GSD CPM Project Manager, GSD CPM Clerical, Auditor's Office, County
Counsel's Office, County Administrator's Office, County Administrator's Office
C.53
To:Board of Supervisors
From:Julia R. Bueren, Director of Public Works
Date:April 3, 2012
Contra
Costa
County
Subject:Award of Construction Trade Contract for Trade Bid Package 7A for the West County Health Center Project,
13601 San Pablo Avenue, San Pablo
Labor Agreement with the Contra Costa Building
RECOMMENDATION(S): (CONT'D)
and Construction Trades Council to comply with the requirements of the County’s Project
Labor Agreement policy.
5. DIRECT that Vomar shall submit two good and sufficient surety bonds (performance
bond and payment bond) in the amount of $154,479 each and that Vomar and its
subcontractors shall sign a Project Labor Agreement for the project; and ORDER that, after
Vomar has signed the trade contract and returned it, together with the bonds, the signed
Project Labor Agreement, evidence of insurance, and other required documents, and the
Deputy General Services Director has reviewed and found them to be sufficient, the Deputy
General Services Director, or designee, is authorized to sign the trade contract for this Board.
6. AUTHORIZE the Deputy General Services Director, or designee, to exonerate any bid
bonds posted by the bidders after execution of the above trade contract.
7. AUTHORIZE the Deputy General Services Director, or designee, to sign any escrow
agreements prepared for this project to permit the direct payment of retentions into escrow
or the substitution of securities for monies withheld by the County to ensure performance
under the trade contract, pursuant to Public Contract Code Section 22300.
8. AUTHORIZE the Deputy General Services Director, or designee, to order changes or
additions to the trade contract work pursuant to Public Contract Code Section 20142.
9. DELEGATE, pursuant to Public Contract Code Section 4114, the Board's function under
Public Contract Code Sections 4107 and 4110, with regards to subletting and
subcontracting, to the Deputy General Services Director, or designee.
10. DELEGATE, pursuant to Labor Code Section 6705, to the Deputy General Services
Director or to any registered civil or structural engineer employed by the County the
authority to accept detailed plans showing the design of shoring, bracing, sloping or other
provisions to be made for worker protection during trench excavation covered by that
section.
11. DECLARE that, should the award of the trade contract to Vomar be invalidated for any
reason, the Board would not in any event have awarded the contract to any other bidder, but
instead would have exercised its discretion to reject all of the bids received. Nothing herein
shall prevent the Board from re-awarding a trade contract to another bidder in cases where
the successful bidder establishes a mistake, refuses to sign the trade contract, or fails to
furnish required bonds or insurance in accordance with Public Contract Code Sections
5100-5107.
FISCAL IMPACT:
The estimated total project cost is $45 million. Funding in the amount of $12 million is from
The estimated total project cost is $45 million. Funding in the amount of $12 million is from
a federal Health Resources and Services Administration (“HRSA”) grant, provided under
the American Recovery and Reinvestment Act of 2009. The remaining balance of $33
million is provided through bond financing and dedicated revenue within the Hospital
Enterprise Fund.
BACKGROUND:
The West County Health Center (“WCHC”) project involves constructing a new 2-story,
53,000-square-foot health center in San Pablo. The new WCHC will serve the region by
providing outpatient and ancillary services in a modern and efficient facility. In addition, a
new 315-stall, 3-level parking structure will be built adjacent to the WCHC. The
“Construction Manager At-Risk” (“CM At-Risk”) project delivery method is being utilized
on the project. Utilizing this method involves overlapping multiple design and construction
phases in order to fast-track the project. With the CM At-Risk project delivery method,
multiple trade bid packages (e.g., earthwork, piles, concrete, framing, mechanical, and
electrical) are developed and issued for bidding. Twenty-eight trade contracts (for earthwork
phase 1, pile foundations, general requirements work, structural steel and metal decking,
concrete, elevators, miscellaneous metals/stairs, curtain wall, drywall/plaster, fire
protection, plumbing, mechanical, electrical, site utilities,
roofing/waterproofing/architectural sheet metal, earthwork phase 2, millwork,
doors/frames/hardware, acoustical ceilings, painting, site concrete/caulking, flooring,
landscaping and irrigation, miscellaneous specialties, miscellaneous metal phase 2,
overhead coiling doors and grills, ceramic tile, and window shades) have already been
awarded by the Board. A trade bid package for building signage was subsequently
developed and issued for bidding.
Bids were received for Trade Bid Package 7A and opened by the General Services
Department on March 20, 2012. The bid results for Trade Bid Package 7A is as follows:
Bidder Base Bid
Vomar Products, Inc., Canoga Park $154,479.00
Arrow Sign Company, Oakland $188,502.60
Ellis & Ellis Sign Systems, Sacramento $200,237.98
VKK Signmakers, Inc., Redwood City $258,035.00
Priority Architectural Graphics, San Francisco $315,308.75
For Trade Bid Package 7A, two of the five bids were below the CM At-Risk's estimate of
$200,000. Vomar submitted the lowest responsive and responsible bid of $154,479, which
is $34,023.60 less than the next lowest bid. Staff recommends that the trade contract for
Trade Bid Package 7A, consisting of building signage, be awarded to Vomar.
With the CM At-Risk project delivery method, the County contracts directly with the
various trade contractors, and Turner, as CM At-Risk, manages the trade contracts with a
Guaranteed Fixed Price and Guaranteed Completion Date. With award of the above trade
contract for building signage, the total amount of trade contracts to date is $23,532,421.
Recommendations for the award of other trade contracts will come before the Board at
future dates.
The County’s CM At-Risk, Turner, has submitted its documentation of good faith effort to
comply with the requirements of the County's Outreach Program for Trade Bid Package 7A.
The Contract Compliance Officer has reported that Turner has documented an adequate
good faith effort for this trade contract.
Pursuant to the County’s Project Labor Agreement (PLA) policy, a PLA is required for all
trade contracts on this project. Vomar has signed a PLA, which contains a local hire
provision consistent with the Disposition and Development Agreement between the City of
San Pablo Redevelopment Agency and the County. As a condition of trade contract award,
Vomar’s subcontractors will also be required to sign the PLA.
The general prevailing rates of wages, which shall be the minimum rates paid on this
project, are on file with the Clerk of the Board, and copies are available to any party upon
request.
CONSEQUENCE OF NEGATIVE ACTION:
Failure to award the trade contract would delay the project and could potentially result in
the WCHC not being built and the loss of $12 million in federal stimulus money.
CHILDREN'S IMPACT STATEMENT:
None.