HomeMy WebLinkAboutMINUTES - 03132012 - SD.4RECOMMENDATION(S):
CONSIDER accepting eBART status report, as recommended by Supervisor Piepho.
FISCAL IMPACT:
Information item only. No fiscal impact
BACKGROUND:
See attached presentation materials on the eBART construction. Construction is underway
at the Pittsburg/Bay Point BART Station and Phase I of the eBART project is nearing
completion. The next phase is the eBART Next Segment study which will begin now. The
study will examine station sites beyond the planned Hillcrest Station and is looking at five
opportunities for an eBART station. The station sites to be evaluated are along the Bypass,
and are: Laurel Road, Lone Tree Way, Sand Creek Road, Balfour Road, and near Marsh
Creek Road.
CONSEQUENCE OF NEGATIVE ACTION:
None.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 03/13/2012 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
ABSENT:Federal D. Glover, District V
Supervisor
Contact: Jen Quallick
925.252-4500
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: March 13, 2012
David Twa, County Administrator and Clerk of the Board of Supervisors
By: June McHuen, Deputy
cc:
SD. 4
To:Board of Supervisors
From:Tiffany Lennear, Clerk of the Board
Date:March 13, 2012
Contra
Costa
County
Subject:Status Report on eBART Project and Introduction of Next Segment Study
CHILDREN'S IMPACT STATEMENT:
None.
ATTACHMENTS
eBart Briefing
Board of Supervisors
2eBART Update TodayConstruction Progress, Contract 1Next Segment Study
3Phase I construction: transfer platform
Phase I construction: transfer platform 4
5Phase I construction: transfer platform
6Phase I construction: duct bank installation
7Phase I construction: duct bank installation completion
Phase 1 Construction: median barriers 8
9Phase I construction: median barriers
10Phase I construction: median barriers
11eBART Next Segment Study
12eBART Next Segment Alignments
13eBART Next Segment: Example of Laurel Road Station Area
14eBART Next Segment: Example of Laurel Road Station Area
15Next Segment Outreach Public information & input on project & stations:•Town Hall meetings with Director Keller•City Council presentations •Board of Supervisor presentations•Tri Delta Board presentations•ePPAC discussions•BART website at www.bart.gov
16Next Segment Introduction Outreach Dates •Pittsburg City CouncilJanuary 30•Oakley City CouncilFebruary 14•Tri Delta Board presentation February 22•Brentwood City CouncilFebruary 28•Board of Supervisorstoday•Antioch City CouncilMarch 13•Director Keller Town Hall June•ePPAC discussionsAs scheduled•BART websiteOngoing
17Next Segment Outreach Next Segment public input on:Station sitesLand uses at station and surrounding stationAccess Ridership estimatesConceptual engineeringConceptual station drawingsConceptual cost estimates
18Upcoming EventsAdvertise Contract 2: Hillcrest Parking Lot/Maintenance Facility ConstructionMarchNext ePPAC Meeting May 10