SUBJECT: In the Matter of Award of Contract for the 1985 Signal and
Flasher Project, Project No. 0662-6R4289-84, Countywide Area.
Bidder Total Amount Bond Amounts
William G. McCullough Company 159,094.92 Payment $79,547.46
PO Box 426 Faith. Perf. $159,094.92
Antioch, CA 94509-0042
Richard A. Heaps Electrical Contractor, Inc.
Steiny and Company, Inc.
Continental Electric
Rosendin Electric, Inc.
The above-captioned project and the specifications therefor being
approved, bids being duly invited and received by the Public Works Director;
and
The Public Works Director recommending that the bid listed first
above is the lowest responsible bid and this Board concurring and so
finding;
IT IS BY THE BOARD ORDERED, that the contract for the furnishing
of labor and materials for said work is awarded to said first listed
bidder at the listed amount and at the unit prices submitted in said
bid; and that said contractor shall present. two good and sufficient surety
bonds as indicated above; and that the Public Works Department shall
prepare the contract therefor.
IT IS FURTHER ORDERED that, after the contractor has signed the
contract and returned it together with bonds as noted above and any required
certificates of insurance—or other required documents, and the Public
Works Director has reviewed and found them to be sufficient, the Public
Works Director is authorized to sign the contract for this Board.
IT IS FURTHER ORDERED that, in accordance with the project specifica-
tions and/or upon signature of the contract by the Public Works Director,
any bid bonds posted by the bidders are to be exonerated and any checks or
cash submitted for bid security shall be returned.
I hereby certify tha:this is a true and correct copy of
an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED; FEB 11 1986
PHIL BATCHELOR,* Clerk of the Board
of Supervisors and County Administrator
Orig.Dept.: Public Works Department (D/C)
cc: County Administrator By , Deputy
Auditor-Controller
P. W. Accounting Division
Contractor
Award.d3lSig.t2
i