HomeMy WebLinkAboutMINUTES - 01102012 - C.68RECOMMENDATION(S):
1. APPROVE the design, plans, and specifications for the above project.
2. DETERMINE that the bids submitted by Orea Construction and Murray Building were
non-responsive; and REJECT the bids on that basis.
3. AWARD the construction contract for the above project in the amount of $390,470 to
Vila Construction Company ("Vila"), the lowest responsive and responsible bidder for the
subject project; and DIRECT the General Services Deputy Director, or designee, to prepare
the contract.
4. DETERMINE that Vila has documented an adequate good faith effort to comply with the
specifications and the requirements of the County's Outreach Program in connection with
the above project and WAIVE any irregularities in such compliance.
5. DIRECT that Vila shall submit two good and sufficient security bonds (performance and
payment bonds), each in the amount of $390,470.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 01/10/2012 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
ABSENT:Gayle B. Uilkema, District II
Supervisor
Contact: Rob Lim, (925) 313-7200
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: January 10, 2012
David Twa, County Administrator and Clerk of the Board of Supervisors
By: June McHuen, Deputy
cc: GSD Administration, GSD Accounting, GSD CPM Division Manager, GSD CPM Project Manager, GSD CPM Clerical, Auditor's Office, County
Counsel's Office, County Administrator's Office, County Administrator's Office
C. 68
To:Board of Supervisors
From:Steve Silveira, Deputy General Services Director
Date:January 10, 2012
Contra
Costa
County
Subject:Award of Construction Contract for the Antepartum Room Remodel Project at Contra Costa Regional
Medical Center, 2500 Alhambra Avenue, Martinez
6. ORDER that, after Vila has signed the contract and returned it, together with the bonds,
evidence of insurance, and other required documents, and the General
RECOMMENDATION(S): (CONT'D)
Services Deputy Director has reviewed and found them to be sufficient, the General
Services Deputy Director, or designee, is authorized to sign the contract for this Board.
7. AUTHORIZE the General Services Deputy Director, or designee, to exonerate any bid
bonds posted by the bidders after execution of the above contract.
8. AUTHORIZE the General Services Deputy Director, or designee, to sign any escrow
agreement prepared for this project to permit the direct payment of retentions into escrow or
the substitution of securities for monies withheld by the County to ensure performance
under the contract, pursuant to Public Contract Code Section 22300.
9. AUTHORIZE the General Services Deputy Director, or designee, to order changes or
additions to the work pursuant to Public Contract Code Section 20142.
10. DELEGATE, pursuant to Public Contract Code Section 4114, the Board's function
under Public Contract Code Sections 4107 and 4110, with regards to subletting and
subcontracting, to the General Services Deputy Director, or designee.
11. DECLARE that, should the award of a contract to Vila be invalidated for any reason,
the Board would not in any event have awarded the contract to any other bidder, but instead
would have exercised its discretion to reject all of the bids received. Nothing herein shall
prevent the Board from re-awarding a contract to another bidder in cases where the
successful bidder establishes a mistake, refuses to sign the contract, or fails to furnish
required bonds or insurance in accordance with Public Contract Code Sections 5100-5107.
FISCAL IMPACT:
The project is funded by the Health Services Department's Enterprise Fund (EF-1), fiscal
year 2011/2012 budget.
BACKGROUND:
The project involves remodeling the former antepartum room (located on the fifth floor of
the hospital building) into a labor and delivery room at the Contra Costa Regional Medical
Center ("CCRMC"). Adding a labor and delivery room will help alleviate a shortage of
these facilities. The antepartum testing function was relocated to Building One on the
campus in a previous project. The project scope also involves remodeling a nurse's station
and upgrading the floor security system.
Plans and specifications for the project were prepared for the General Services Department
by Kaplan McLaughlin Diaz, and filed with the Clerk of the Board by the General Services
Deputy Director. Bids were received and opened by the General Services Department on
November 17, 2011, and the bid results are as follows:
BIDDER BASE BID
Orea Construction, Dublin $279,500
Murray Building, Inc., Sonoma $319,000
Vila Construction, Richmond $390,470
Angotti & Reilly, San Francisco $392,000
Cahil Contractors, San Francisco $410,930
W.A. Thomas Co., Inc., Martinez $523,000
Two of the six bids received were below the architect's estimate of $349,200. In evaluating
the apparent low bid submitted by Orea Construction, it was determined that the bid did not
comply with the County's Outreach Program requirements and, therefore, the bid was
non-responsive. In evaluating the apparent second low bid submitted by Murray Building, it
was determined that the bid did not comply with the Mandatory Subcontracting Minimum
(MSM) requirement for this project and did not comply with the bidder responsibility
requirements, including sufficient similar project experience. Vila's bid was also evaluated
and determined to be responsive and responsible. Therefore, Vila submitted the lowest
responsive and responsible bid, which is $41,270 higher than the architect's estimate. The
Health Services Department has sufficient funding to cover the additional costs. Staff
recommends that the Board reject as non-responsive the bids submitted by Orea
Construction and Murray Building and award the construction contract for this project to
Vila for a total award amount of $390,470.
Letters were previously sent notifying Orea Construction and Murray Building of the above
deficiencies with their bids and affording them an opportunity to appeal their
disqualification. No appeal was submitted by either bidder.
Vila has submitted its documentation of good faith efforts to comply with the specifications
and requirements of the County's Outreach Program. Staff has determined that Vila has
documented an adequate good faith effort to comply with the requirements of the Outreach
Program and recommends that the Board so determine.
The general prevailing wage rates, which shall be the minimum rates paid on this project,
are on file with the Clerk of the Board, and copies are available to any party upon request
CONSEQUENCE OF NEGATIVE ACTION:
Without an additional labor and delivery room, the CCRMC will be unable to meet current
service demands. In addition, the space available in the antepartum room will remain
under-utilized.
CHILDREN'S IMPACT STATEMENT:
Not applicable.