HomeMy WebLinkAboutMINUTES - 12132011 - C.11RECOMMENDATION(S):
ADOPT Resolution No. 2011/492 approving the second extension of the Subdivision
Agreement for
subdivision SD 05-08950 for a project being developed by Avalon Bay Communities, Inc.,
as recommended by
the Public Works Director, Pleasant Hill (Contra Costa Centre) area. (District V)
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
The improvements have been completed with the exception of punch list items. Granting an
extension gives the developer an additional year to complete the minor deficiencies and
keeps the bonding current during the warranty period.
CONSEQUENCE OF NEGATIVE ACTION:
The Subdivision Agreement will not be renewed if the extension is not granted.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 12/13/2011 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: J. LaRocque, (925)
313-2315
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: December 13, 2011
David Twa, County Administrator and Clerk of the Board of Supervisors
By: STACEY M. BOYD, Deputy
cc: K. Guruwaya, Connie Sumpter
C. 11
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:December 13, 2011
Contra
Costa
County
Subject:Approving the second extension of the Subdivision Agreement for subdivision SD 05-08950
CHILDREN'S IMPACT STATEMENT:
Not applicable.
ATTACHMENTS
Resolution No. 2011/492
sd 05-08950